Home› Data centres in Malaysia
Data centres in Malaysia · Updated 20 Nov 2026

Data Centres in Malaysia by State: Map, Power and Water

Every Malaysian data centre with a public source: 72 running, being built or announced, by State, on a map, with published power (MW) and water use.

中文版 →
Scott Seow
Scott Seow
Probationary Estate Agent
Key takeaways
  • 72 data centres and campuses with a public source: 27 running, 26 being built and 19 announced (land bought or approved).
  • Selangor and Johor have 25 each. Johor's are the biggest: about 3,700MW of the 5,850MW published nationwide.
  • Officially, running data centres drew 1,102MW of the 2,050MW approved for them (April 2026) and used about half the water approved.
  • No data centre publishes what it actually draws. The MW on this page is the size each company gives.
72data centres and campuses on this list
27running
26being built
19announced (land bought or approved)
14marked ⚠ needs checking

This page lists every data centre in Malaysia that has a public source: a company or Bursa filing, a government answer, or two independent reports. It is grouped by State, shows each one on a map, and is updated with every data-centre story we publish, plus a full check every quarter.

How much power and water do they actually use?

No data centre publishes its own meter reading, so these are the government's totals for the whole country, from written answers to Parliament.

Power actually drawn1,102MWof the 2,050MW approved for data centres that are running (54%), as at April 2026Energy Minister's written answer to Parliament, Jun 2026 (via w.media)
Water actually usedabout 28.7 million litres a day51.4% of the 55.83 million litres a day approved for data centres (our sum from the ministry's percentage)Energy Minister's written answer to Parliament, Jun 2026 (via w.media)
Power approved (all projects)12.3GWof electricity supply approved for data-centre projects as at August 2026; their maximum demand is expected to reach 8.39GW by 2030Energy Minister's written answer to Parliament (via The Star, 20 Oct 2026)
Water approved (all projects)445 million litres a dayapproved for data-centre projects in Selangor, Johor and Negeri Sembilan from 2025 to 2030. Only 63.90 million (14.36%) is for data centres already running (June 2026)Energy Minister's written answer to Parliament (via The Star, 20 Oct 2026)

Data centres by state

StateConfirmedRunningBeing builtAnnouncedPublished MW*
Johor2571083,739
Selangor2511681,424
Kuala Lumpur7421202
Negeri Sembilan5041350
Penang431097
Kedah21104
Perak101010
Pahang1001–
Sarawak211017
Perlis0000–
Melaka0000–
Terengganu0000–
Kelantan0000–
Sabah0000–
Labuan0000–
Malaysia722726195,843

*Published MW adds up the planned or built capacity that each company or filing gives (mostly computer load; a few are power supply). It is not what they draw today. Many sites publish no MW, so the real total is higher.

Map and table of every data centre

Running Being built Announced · Filled = the building or plot Ring = park or town only (≈)
Tap a dot for its name, size, “Details” and “Open in Google Maps”. 38 pins are on the site itself; 37 show only the park or town, because the plot is not published. No pin yet (location not published): AirTrunk JHB3 and JHB4; Princeton Digital JH2; EdgeConneX Johor; TM SJDC.

Table: tap a heading to sort (tap again to reverse). Tap a name for its full card and sources; tap 📍 to find it on the map.

Bridge Data Centres MY06 Johor508Running38 (first phase)4 MLD recycled waterKulai (Sedenak)✅
AirTrunk JHB1 and JHB2 Johor420Running––Johor Bahru; Iskandar Puteri✅
DayOne, Nusajaya Tech Park and Kempas Tech Park Johor390Running–Recycled water (no figure)Iskandar Puteri; Johor Bahru✅
YTL Green Data Center Park Johor298 contractedRunning––Kulai✅
Princeton Digital JH1 Johor200Running––Kulai (Sedenak)✅
Equinix JH1 Johor–Running––Gelang Patah✅
TM Iskandar Puteri Data Centre (IPDC) Johor–Running––Iskandar Puteri✅
Vantage JHB1 (formerly Yondr) Johor300Being builtabout 73–Kulai (Sedenak)✅
STACK Infrastructure JHB01 Johor216Being builtabout 27–Gelang Patah✅
TM Nxera campus, Iskandar Puteri Johor200Being builtabout 41.5–Iskandar Puteri✅
Digital Halo JHB1 Johor120Being built20.5–Iskandar Puteri✅
Epoch Digital EMY1 Johor120Being built20.4–Iskandar Puteri✅
Racks Central RCJM campus Johor90 first phaseBeing built––Pasir Gudang⚠
Equinix JH2 Johor7.2Being built––Gelang Patah✅
ZDATA / Computility AI data centre, Gelang Patah Johor–Being built38.5 ⚠Up to 4 MLD recycled waterGelang Patah⚠
STT Johor 1 Johor–Being built––Gelang Patah⚠
EdgeConneX JohorJohor–Being built––Johor (not published)⚠
Princeton Digital JH2Johor300Announced––Senai✅
NTT DATA Johor Bahru campus (JHB10) Johor290Announced68.5–Gelang Patah✅
AirTrunk JHB3 and JHB4Johor280Announced––Iskandar Puteri✅
Data Cloud Innovation, Nusa Cemerlang Johor–Announced18.4–Iskandar Puteri✅
Microsoft land in Johor Johor–Announced284+ (three parks)–Kulai; Iskandar Puteri✅
KNBDC, QUANTUM Edge Johor–Announced49.6–Kulai✅
DayOne, Tanjung Kupang land (from Paragon Globe) Johor–Announced65.3–Iskandar Puteri✅
Digital Edge, Bandar Cemerlang Johor–Announced49.7–Kota Tinggi✅
Bridge Data Centres MY01 and MY02 Selangor98Running––Cyberjaya✅
NEXTDC KL1 Selangor65Running––Petaling Jaya✅
AIMS Cyberjaya Selangor30 up toRunning––Cyberjaya✅
NTT Cyberjaya campus Selangor22 whole buildingRunning––Cyberjaya✅
STT Kuala Lumpur 1 (with Basis Bay) Selangor16.5Running––Cyberjaya✅
Google, Elmina Business Park (first campus) Selangor–Runningabout 49–Sungai Buloh (Elmina)✅
Vantage KUL1 (Cyberjaya I) Selangor–Running––Cyberjaya✅
Equinix KL1 Selangor–Running––Cyberjaya✅
TM Klang Valley Data Centre (KVDC) Selangor–Running––Cyberjaya✅
TM Kelana Jaya Data Centre (KJDC) Selangor–Running––Kelana Jaya✅
Basis Bay Cyberjaya DC1, DC2 and Glenmarie Selangor–Running––Cyberjaya; Shah Alam✅
Vantage KUL2 (Cyberjaya II) Selangor400Being built32–35–Cyberjaya✅
EdgeConneX Cyberjaya Selangor200Being builtabout 30–Cyberjaya⚠
Google, Elmina Business Park Phase 2 Selangor–Being builtabout 77–Sungai Buloh (Elmina)✅
Google, Eco Business Park V Selangor–Being built150.6 (two deals)–Puncak Alam✅
Hyperscale data centre, Bandar Serendah Selangor–Being built––Serendah✅
Data centre at Banting Tech Park (old Megasteel site) Selangor–Being built––Banting⚠
Global Data Infrastructure, COMPASS @ Kota Seri Langat Selangor210Announced36–Banting✅
AIMS 200MW AI data centre, Cyberjaya Selangor200 up toAnnouncedabout 10–Cyberjaya✅
Digital Cosmos, Cyberjaya Selangor182 power supplyAnnounced45.89.41 MLD neededCyberjaya✅
Amazon (AWS) land, Dengkil Selangor–Announced45.46–Dengkil✅
DayOne, Southville City Selangor–Announced78.8–Dengkil (Southville City)✅
DayOne, Kapar Selangor–Announcedabout 157–Kapar, Klang✅
Bridge Data Centres, IOI Industrial Park @ Banting Selangor–Announced136.03–Banting✅
Equinix KL2 Selangor–Announced––Cyberjaya✅
Bridge Data Centres MY03 Kuala Lumpur48Running––Bukit Jalil✅
AIMS Kuala Lumpur (Menara AIMS and Bangunan AIMS) Kuala Lumpur–Running––KL city centre✅
TM Brickfields Data Centre (BFDC) Kuala Lumpur–Running––Brickfields✅
YTL Sentul Data Center 1 Kuala Lumpur–Running––Sentul⚠
EdgeConneX Bukit Jalil and KL city centre Kuala Lumpur89Being built––Bukit Jalil; KL city centre⚠
EXSIM hyperscale data centre, Bukit Jalil Kuala Lumpur–Being built––Bukit Jalil⚠
MRCB data centre, Bukit Jalil Kuala Lumpur65Announcedabout 9.2–Bukit Jalil✅
Nexus Yang Green Data Centre Campus Negeri Sembilan350Being built157–Senawang, Seremban✅
Google, Springhill Industrial Park Negeri Sembilan–Being built38965 MLD plant (Google pays; shared with homes)Port Dickson✅
Green data centre by US investors, Nilai Negeri Sembilan–Being built––Nilai⚠
Shinsei Malaysia 1 Negeri Sembilan–Being built––Labu (Enstek)⚠
Tera Data Centers, Eco Business Park 7 Negeri Sembilan–Announced221.7–Port Dickson (Bukit Pelandok)✅
Open DC PE2 Penang30Running10–Bayan Lepas✅
Open DC PE1 Penang–Running––Bayan Baru⚠
TM SJDCPenang–Running––Penang (free industrial zone)✅
Deep Source AI data centre (former Southern Steel plant) Penang67Being built15.6–Prai✅
Open DC D8-1 Kedah4Running––Bukit Kayu Hitam✅
AREA data centre campus Kedah–Being built30 (+126 option)–Bukit Kayu Hitam⚠
Silverstreams data centre Perak10.06Being built––Bagan Datuk✅
Deep Source AI data centres, MCKIP Pahang–Announced435.6–Kuantan (Gebeng)✅
irix DC @ Santubong 1 Sarawak–Running––Santubong, Kuching✅
GDC Kuching (KCH1), FutureData Park Sarawak17Being built––Kota Samarahan⚠

Power (MW) is the size the company or filing gives, mostly the power for the computers. It is not what the site draws today: no data centre publishes that (the country’s total is near the top of this page). “–” = not published.
💧 Water: only a few sites give a figure, and none is a meter reading. MLD = million litres a day.
Sure? ✅ confirmed · ⚠ needs checking (the reason is on its card).

How to read this list

  • Running / Being built / Announced: "Announced" means land has been bought or an approval given. Agreements, MoUs or studies with no land go on each State's "Checked and left out" list, with the reason.
  • ✅ Confirmed = a company, Bursa/HKEX or government source, or two independent sources. ⚠ Needs checking = something is missing or out of date; the reason is on the card.
  • ⚡ Power (MW): unless it says otherwise, this is the power for the computers (IT load). TNB's supply figure is bigger because it also covers cooling.
  • 💧 Water: only a few sites publish a water figure; those are shown.
  • Campuses with several buildings are shown as one card. In-house server rooms are listed only when a source names them.

Malaysia as a whole: official figures

Running, but location not published

  • Microsoft 'Malaysia West' cloud region: Running since 28 May 2025. Three availability zones in Greater Kuala Lumpur; Microsoft does not say where its buildings are. A second region is planned in Johor. (The Star)
  • AWS Asia Pacific (Malaysia) region: Running since Aug 2024. Three availability zones; AWS does not say where its buildings are. US$6.2b planned to 2038. Its own land deal in Dengkil is listed under Selangor. (AWS (Business Wire))
  • Pusat Data Sektor Awam (PDSA), the government's data centre: Started in 2011 by MAMPU; now run by Jabatan Digital Negara (JDN) with MyGovCloud. It hosts more than 1,000 servers for 120 agencies. Its location is not published. (MyGOV portal)

Data centres in each state

Johor25 confirmed

By far the biggest data-centre state. 16 of the 27 projects the Data Centre Task Force approved up to July 2026 are in Johor. The main clusters are Sedenak Tech Park and Eco Business Parks in Kulai/Senai, and Nusajaya Tech Park, Nusa Cemerlang and Gelang Patah in Iskandar Puteri, plus Pasir Gudang and Kota Tinggi. Water: in 2024, 13 Johor data centres asked for 29.1 million litres a day and were given 6.10 million (21%). Since Aug 2025 Johor charges data centres RM5.33 per m³, and new projects are pushed to recycled water (IWK can supply 12 million litres a day of reclaimed water to two data centres).

Bridge Data Centres MY06

Running
WhoBridge Data Centres (Bain Capital); ByteDance was the launch customer
WhereSedenak Tech Park, Kulai
StatusRunning since Oct 2022 (first phase opened with ByteDance), with more buildings being added
LandFirst phase on 38 acres
⚡ PowerBridge now lists 508MW of computer load across 15 buildings, 275kV supply (first phase: 110MW, 3 buildings)
💧 WaterUses reclaimed water: 4 million litres a day of treated sewage from IWK's JB-Pelangi plant goes to Bridge's water reclamation plant
CostNot published

DayOne, Nusajaya Tech Park and Kempas Tech Park

Running
WhoDayOne
WhereNusajaya Tech Park (Iskandar Puteri) and Kempas Tech Park (Johor Bahru)
StatusRunning since 2023, two campuses
LandNot published
⚡ PowerDayOne's page says 390MW in service (it also says 'over 478MW' operational). Buys solar power from TNB under the CRESS scheme
💧 WaterNot published. DayOne's Malaysia II unit gets recycled water from Johor Special Water (IWK)
CostNot published
DayOne is also buying 65 acres in Tanjung Kupang from Paragon Globe (listed separately).

YTL Green Data Center Park

Running
WhoYTL Power International (YTL Data Center Holdings)
WhereKulai
StatusRunning. 298MW contracted, about 70% handed over to customers (mid-2026). YTL AI Cloud's Nvidia data centre (about 20MW) opened Nov 2025
LandNot published
⚡ Power298MW contracted. Planned capacity raised from 600MW to 1.2GW (analysts, Jun 2026). 215MW of solar on site due by end-2026
💧 WaterNot published
CostNot published

Princeton Digital JH1

Running
WhoPrinceton Digital Group
WhereSedenak Tech Park, Kulai
StatusRunning; first phase delivered, third building done, fourth being built. US$1.3b financing secured Nov 2026
LandNot published (inside Johor Corporation's 300-hectare Sedenak Tech Park)
⚡ Power200MW across four buildings
💧 WaterNot published
CostNot published

TM Nxera campus, Iskandar Puteri

Being built
WhoTM Nxera (Telekom Malaysia and Singtel's Nxera)
WhereIskandar Puteri
StatusGroundbreaking Jul 2024; first phase due to open in 2026
LandAbout 168,000 m² (about 41.5 acres)
⚡ PowerFirst phase 64MW, can grow to 200MW. 280MW supply agreement with TNB (Jan 2026)
💧 WaterNot published
CostOver RM1b

Digital Halo JHB1

Being built
WhoDigital Halo Pte Ltd (Singapore)
WhereNusa Cemerlang Industrial Park, Iskandar Puteri
StatusFirst phase (20MW) topped out Apr 2026, fully leased to one customer
Land20.46 acres, bought from Crescendo for RM115.87m
⚡ PowerFirst phase 20MW; campus 120MW; 150MW supply agreement with TNB
💧 WaterNot published
CostNot published
✅ Confirmed · Sources: w.media (2026-04) · DCD (TNB 150MW) (2026)

Epoch Digital EMY1

Being built
WhoEpoch Digital (an Actis portfolio company); first phase contracted to BytePlus
WhereNusa Cemerlang Industrial Park, Iskandar Puteri
StatusNearly built in Apr 2026 (AIIB); ready for service Q4 2026 (Epoch). Bringing more banks into its loan was delayed in Nov 2026
Land82,526 sq m (20.4 acres), freehold
⚡ PowerFirst phase 60MW; campus 120MW (IT load). Target PUE 1.35
💧 WaterNot published. Target water use 1.6 litres per kWh, hybrid cooling
CostAbout US$870m (AIIB); bank loan US$488m (about RM1.9b)

Racks Central RCJM campus

Being built
WhoRacks Central (Singapore)
WhereIskandar Halal Park, Pasir Gudang
StatusPhase 1 (RCJM1) at third-floor stage (Jun 2026), due to open Q1 2027. Three more developments planned
LandNot published
⚡ PowerPhase 1 90MW; 510MW planned for the whole campus
💧 WaterNot published
CostNot published
⚠ Only one news outlet; the 510MW figure is the company's plan.

ZDATA / Computility AI data centre, Gelang Patah

Being built
WhoComputility Technology (ZDATA Technologies, China)
WhereNusajaya Industrial Park 2, Gelang Patah
StatusBeing built. Its water recycling plant opened Mar 2026; a green-power deal says operations start in 2028
LandProbably the 38.5 acres next to Taman Nusa Bayu that Computility bought from Tropicana for RM240m (RM143 psf; deal signed 9 Oct 2024). Not confirmed
⚡ PowerNot published
💧 WaterCooled only with reclaimed water: up to 4 million litres a day (the first treatment plant handles about 4 million litres a day; four plants planned)
CostAbout RM8b
⚠ Land not confirmed: Tropicana's filing puts Computility's 38.5 acres next to Taman Nusa Bayu, where this pin is, but no source links the two.

EdgeConneX Johor

Being built
WhoEdgeConneX
WhereJohor
StatusIndustry lists say it is being built; EdgeConneX says it is deploying 500MW+ across Cyberjaya and Johor
LandNot published
⚡ PowerNot published for Johor alone
💧 WaterNot published
CostNot published
⚠ Site and size need checking.
⚠ Needs checking · Sources: TechWire Asia (2026-07) · Baxtel (seen 2026-11-16)
📍 Location not published

Princeton Digital JH2

Announced (land or approval)
WhoPrinceton Digital Group
WhereEco Business Park, Mukim Senai (16 km from JH1)
StatusPlanned (five buildings)
LandNot published
⚡ Power300MW
💧 WaterNot published
CostNot published
📍 Location not published

NTT DATA Johor Bahru campus (JHB10)

Announced (land or approval)
WhoNTT DATA (Global Data Centers); title held by NTT Global Data Centers JHB1 Sdn Bhd
WhereGelang Patah (Mukim Pulai), Iskandar Puteri; next to Taman Nusa Bayu and Taman Laman Setia
StatusLand bought from Tropicana (deal Aug 2024); title received Apr 2026. Six buildings planned; in Dec 2024 NTT said the first (48MW) was planned for Apr 2027. Construction start not yet announced
Land68.5 acres, freehold; RM383m (about RM128 psf), from Tropicana
⚡ PowerAbout 290MW of computer load planned (six buildings); first building 48MW
💧 WaterAir-cooled chillers in a closed loop: filled once, no continuous top-up (NTT)
CostNot published

AirTrunk JHB3 and JHB4

Announced (land or approval)
WhoAirTrunk
WhereIskandar Puteri, close to JHB1 and JHB2
StatusAnnounced 30 Apr 2026; opening dates not given
LandNot published
⚡ PowerMore than 280MW of computer load (both campuses)
💧 WaterNot published
CostRM12b (US$3b)
📍 Location not published

Data Cloud Innovation, Nusa Cemerlang

Announced (land or approval)
WhoData Cloud Innovation Sdn Bhd (owned by Magma Holding Company Limited, UK)
WhereNusa Cemerlang Industrial Park, Iskandar Puteri
StatusLand deal signed 6 Dec 2024 for a data centre; completed 12 Jan 2026. No building plan, size or opening date published
Land18.4 acres (74,296 sq m), freehold, one amalgamated title; RM119.96m (RM150 psf), from Crescendo (Panoramic Industrial Development)
⚡ PowerNot published
💧 WaterNot published
CostNot published
Data Center Map lists this land as DAMAC Digital JHB01; DAMAC has not confirmed it.

Microsoft land in Johor

Announced (land or approval)
WhoMicrosoft Payments (Malaysia) Sdn Bhd
WhereEco Business Park VI (Kulai), Eco Business Park I (Iskandar) and Nusa Cemerlang Industrial Park (Iskandar Puteri)
StatusLand bought 2021–2025. Microsoft plans its second Malaysian cloud region in Johor; no opening announced
LandEBP VI 123.141 acres (RM402.3m, 2024); EBP I 138.532 acres (RM693.96m, 2025); Nusa Cemerlang: three plots from Crescendo, the last 22.5 acres for RM119.8m
⚡ PowerNot published
💧 WaterNot published
CostNot published

KNBDC, QUANTUM Edge

Announced (land or approval)
WhoKNBDC Malaysia Five Sdn Bhd (a hyperscale data-centre company)
WhereQUANTUM Edge (Eco Business Park VI area), Kulai
StatusConditional land deal signed 24 Apr 2026; completion expected about 1H 2027
Land49.588 acres in two parcels, RM280.8m (about RM130 psf), from EcoWorld
⚡ PowerNot published
💧 WaterNot published
CostNot published

DayOne, Tanjung Kupang land (from Paragon Globe)

Announced (land or approval)
WhoDayOne (buyer: DayOne Data Centers Malaysia I Sdn Bhd)
WhereGerbang Nusajaya, Mukim Tanjung Kupang, Iskandar Puteri; across Jalan Tanjung Kupang from Nusajaya Tech Park
StatusConditional land deal signed 23 Jun 2026; seller's shareholders approved 27 Oct 2026. Needs planning and Data Centre Task Force approval; completion targeted 2H 2027
Land65.3 acres in two parcels, freehold, now industry titles; RM398.1m (RM140 psf), from Paragon Globe
⚡ PowerNot published
💧 WaterNot published
CostNot published (land RM398.1m)
Also running (smaller and telco data centres)
Checked and left out in Johor (3)
  • YTL Power + JLand gigawatt campus, Sedenak: Partnership announced Aug 2026. Land terms and approvals not disclosed; the 1.3–1.5GW size is an analyst estimate. source
  • Kerjaya Prospek's RM858m fit-out job, Iskandar Puteri: A contractor job at a data centre whose owner is not named; it may be one of the sites above. source
  • Named only on industry lists (Johor): Keppel DC Johor 1; GDC Sedenak SDK1 and SDK2; K2 Data Centres Kulai; BrightRay MY-01; Empyrion Digital MY1; MSFusion (Megaspeed), Kota Tinggi; Global Switch Johor; Open DC JB1 and JB2; VADS Cyberport, Johor Bahru, Medini and Iskandar Puteri. Not yet confirmed from the operators. source

Selangor25 confirmed

Malaysia's second-biggest data-centre state after Johor. Cyberjaya is the old hub; the new campuses are going to Elmina, Puncak Alam, Serendah, Dengkil/Sepang, Kapar and Banting. The state approved 39 data-centre projects from 2021 to 2025. Water: Air Selangor has 16.23% spare treated water (1,055 million litres a day), and the state says it will not approve a data centre without enough water and power. The Rasau scheme is due to add 350 million litres a day, rising to 700 when its first phase is complete. Only one site has published a water figure: Digital Cosmos in Cyberjaya needs at least 9.41 million litres a day.

NEXTDC KL1

Running
WhoNEXTDC (Australian-listed)
WhereSeksyen 51A, Petaling Jaya
StatusRunning since May 2026 (first phase). Five phases planned
LandNot published
⚡ PowerFirst phase 15MW; 65MW of computer load when complete
💧 WaterNot published
CostAbout A$1 billion (about RM2.8b) over time
✅ Confirmed · Sources: TechWire Asia (2026-05) · iTWire (2026-05)

NTT Cyberjaya campus

Running
WhoNTT DATA (Global Data Centers)
WherePersiaran APEC, Cyberjaya
StatusRunning. Six data centres; the newest, CBJ6, opened Oct 2023
LandNot published
⚡ PowerCBJ6: 7MW of computer load. CBJ5 and CBJ6 together: 22MW facility load
💧 WaterNot published
CostCBJ6: over RM234m
✅ Confirmed · Sources: MIDA (NTT release) (2023-10)

Google, Elmina Business Park (first campus)

Running
WhoGoogle (site held through Pearl Computing Malaysia Sdn Bhd; buildings leased from Sime Darby Property)
WhereElmina Business Park, Sungai Buloh
StatusRunning (Google, 4 Nov 2026). Google's first Malaysian data centre and its Google Cloud region
LandAbout 49 acres, built and leased by Sime Darby Property for 20 years (+5+5); rent up to RM2 billion over 20 years (agreed May 2024)
⚡ PowerNot published. Google reports PUE 1.12–1.14 and says it pays for all the electricity its campuses use
💧 WaterNot published
CostPart of the US$2 billion Google announced in May 2024

Vantage KUL1 (Cyberjaya I)

Running
WhoVantage Data Centers
WhereJalan Cyber Point 4, Cyberjaya
StatusRunning. Fourth and last building (KUL14) opened Dec 2025, fully leased to one customer
LandNot published
⚡ PowerKUL14 is 16MW. Vantage does not give the campus total
💧 WaterNot published
CostNot published
✅ Confirmed · Sources: Vantage (Media OutReach) (2025-12-04)

Google, Elmina Business Park Phase 2

Being built
WhoSime Darby Property builds; leased to Pearl Computing Malaysia (Google)
WhereElmina Business Park, Sungai Buloh
StatusBeing built. IJM has the RM1.26b core-and-shell contract for one data-centre block (Oct 2025; analysts expect completion Q2 2027) and a RM873.9m M&E fit-out contract from Pearl Computing
LandAbout 77 acres, 20-year lease (+5+5); rent up to RM5.6 billion over 20 years (agreed Nov 2024, completion 2027)
⚡ PowerNot published
💧 WaterNot published
CostBuild contracts RM2.13b (IJM)

Google, Eco Business Park V

Being built
WhoEcoWorld builds and leases to Pearl Computing Malaysia (Google); Pearl also owns land next door
WhereEco Business Park V, Puncak Alam (Mukim Ijok, Kuala Selangor)
StatusBeing built: Gamuda's RM2.138b build-only contract (two shell-and-core blocks, a substation and a reservoir) runs Q3 2025 to Q3 2027. Google calls its new Puncak Alam campus 'at the planning stage' (Nov 2026). Selangor stopped all development works in Puncak Alam after floods on 6 Nov 2026
LandEcoWorld's build-and-lease: 92.44 acres, 20 years, rent up to RM4.8b. Pearl bought a further 58.187 acres from EcoWorld for RM266.1m (about RM105 psf), completed 22 Dec 2025
⚡ PowerNot published by Google. An architect (KCLA) lists a 160MW campus on 58 acres in Puncak Alam for a client it does not name
💧 WaterNot published
CostBuild contract RM2.138b (Gamuda)

Hyperscale data centre, Bandar Serendah

Being built
WhoAn 'international hyperscaler' that the filings do not name
WhereBandar Serendah, Hulu Selangor
StatusBeing built. Sunway Construction has two build-only contracts: RM1.75b (Apr 2026, Q3 2026 to Q3 2028) and RM1.739b (Nov 2026, Q4 2026 to Q4 2028)
LandNot published. An architect (KCLA) lists a 141-acre Serendah campus for a client it does not name
⚡ PowerNot published. KCLA's campus page says 480MW
💧 WaterNot published
CostBuild contracts RM3.49b (Sunway Construction)
Who owns it is not confirmed. Google named UMW's park in Serendah as a new campus 'at the planning stage' in Nov 2026, but no land deal has been announced there.

Data centre at Banting Tech Park (old Megasteel site)

Being built
WhoA Malaysian data-centre company that the filings do not name
WhereBanting Tech Park, Banting, Kuala Langat
StatusPower works under way: a 33kV interim supply due by 26 Nov 2026, then a 275kV link from the Megasteel substation to 'Consumer Landing Station No. 1' by 15 Jan 2027
LandNot published
⚡ PowerNot published. Lion Group said in 2024 that its land here can draw up to 1,000MW through its own 275kV intake
💧 WaterNot published
CostPower works alone RM142m (Jati Tinggi, two contracts)
⚠ The owner is not named, and the link to Lion Group's land is our reading of the substation name.

Global Data Infrastructure, COMPASS @ Kota Seri Langat

Announced (land or approval)
WhoGlobal Data Infrastructure Sdn Bhd (part of a global data-centre consortium, not named)
WhereCOMPASS @ Kota Seri Langat, Banting, Kuala Langat
StatusLand deal signed 8 Jul 2026; approvals in principle in hand; building to start after completion
Land36 acres, the last plot in the 220-acre park
⚡ Power210MW of computer load; 300 MVA power supply
💧 WaterNot published
CostNot published
✅ Confirmed · Sources: EdgeProp (2026-07-08) · The Edge (2026-08-25)

Digital Cosmos, Cyberjaya

Announced (land or approval)
WhoDigital Cosmos Malaysia Sdn Bhd (owned by Digital Cosmos (S) Pte Ltd, Singapore)
WhereCyberjaya
StatusLand deal signed Aug 2026, conditional on power and water approvals and a new title. Completion expected 4Q 2027
Land36.66 acres (45.81 acres after re-alienation), RM419.05m, from MRCB
⚡ PowerThe sale needs approval for at least 182MW of power supply
💧 WaterThe sale needs confirmation of at least 9.41 million litres of water a day
CostNot published

Amazon (AWS) land, Dengkil

Announced (land or approval)
WhoAmazon Data Services Malaysia Sdn Bhd
WhereH.S.(D) 65882, PT 100115, Mukim Dengkil, Sepang
StatusLand deal signed 28 Sep 2026, still conditional: Sunsuria shareholders, Ministry of Economy, State consent for a foreign buyer, and Data Centre Task Force endorsement. Expected to complete by Q2 2027
Land45.46 acres freehold commercial land, RM316.84m (about RM160 psf)
⚡ PowerNot published
💧 WaterNot published
CostNot published. AWS's Malaysia region (running since Aug 2024, three zones) is a US$6.2b plan to 2038

DayOne, Southville City

Announced (land or approval)
WhoDayOne (WG Malaysia X Sdn Bhd)
WhereSouthville City, Mukim Dengkil, Sepang
StatusLand deal signed Aug 2026, conditional on a new title and approvals from the Data Centre Task Force and PLANMalaysia. Completion expected 2H 2027. In Sep 2026 DayOne and TNB's power arm agreed (non-binding) to study up to 1.5GW of on-site power with batteries for this campus
Land78.80 acres freehold (three parcels), RM617.86m from Mah Sing
⚡ PowerNot published (the 1.5GW on-site power is only a study)
💧 WaterNot published
CostNot published

DayOne, Kapar

Announced (land or approval)
WhoDayOne (WG Malaysia VIII Sdn Bhd)
WhereKapar, Klang
StatusBuying three neighbouring plots; shareholders of the sellers voted on 20 Jul 2026; completion expected 2H 2026
LandAbout 157 acres: Maybulk 58.03 ac (RM278.05m), Eonmetall 66.03 ac (RM273.28m), Leader Steel 33 ac (RM136.56m). RM687.89m in all, about RM101 psf
⚡ PowerNot published. Jati Tinggi has a RM86m job for a 275kV line and landing station at 'Klang Valley Technology Park, Kapar' for a data-centre customer it does not name
💧 WaterNot published
CostNot published
Whether Jati Tinggi's Kapar job is for this campus is not confirmed.

Bridge Data Centres, IOI Industrial Park @ Banting

Announced (land or approval)
WhoBridge Data Centres Malaysia VII Sdn Bhd (Bridge, owned by Bain Capital)
WhereIOI Industrial Park @ Banting, Kuala Langat
StatusLand deal signed 29 Jan 2026
Land136.03 acres (three plots), RM740.68m (about RM125 psf), from IOI Properties
⚡ PowerNot published in the deal. Bridge's website lists a 374MW, 8-building campus called 'MY07' without saying where it is
💧 WaterNot published
CostNot published

Equinix KL2

Announced (land or approval)
WhoEquinix
WhereCyberjaya, less than 1 km from KL1
StatusAnnounced May 2026 (Equinix's fourth Malaysian data centre); opening date not given
LandNot published
⚡ PowerNot published. More than 2,200 cabinets when fully built
💧 WaterNot published
CostUS$190m
✅ Confirmed · Sources: w.media (Equinix release) (2026-05-13)
Also running (smaller and telco data centres)
Checked and left out in Selangor (6)
  • NCT Alliance, NCT Smart Industrial Park: Term sheet only (Sep 2026) for about 100 acres and up to 800MW. No sale agreement yet. source
  • Speedmatrix, Port Klang Free Zone (Pulau Indah): The land lease offer lapsed. source
  • YTL Power + SD Guthrie, Bukit Kerayong (1,623 acres): Planned as an industrial park; no data centre announced on it yet. source
  • Mah Sing–Bridge 'DC Hub' at Southville City (2024): The earlier joint venture did not go ahead; DayOne later bought land in the same township (listed above). source
  • AWS 'KUL' sites in Cyberjaya, Bukit Jalil and Setul: Locations guessed by industry lists. AWS does not publish them. source
  • Smaller rooms named only on industry lists (Selangor): VADS CBJ1, CBJ2, CBJ5, CBJ6, CBJ8; CSF CX1 and CX2 (and tenants Hitachi Sunway, FREENET, SKALI, TelcoHubX, PLTPRO); Open DC CJ1; IP ServerOne CJ1; SKALI Serdang; Maxis i-City; i-City Data Centre (i-Berhad); HDC; Strateq DC-1 and DC-2; MyTelehaus. Not yet confirmed from the operators. source

Kuala Lumpur7 confirmed

Older, smaller city data centres (AIMS in the city centre, TM at Brickfields), with bigger new ones around MRANTI Park in Bukit Jalil. No site publishes its water use.

EdgeConneX Bukit Jalil and KL city centre

Being built
WhoEdgeConneX
WhereMRANTI Park, Bukit Jalil; and central Kuala Lumpur
StatusAnnounced Sep 2023. Industry lists say both are being built; no opening announced
LandNot published
⚡ PowerBukit Jalil nearly 70MW; city centre 19MW (plans)
💧 WaterNot published
CostNot published
⚠ Building status needs checking.

EXSIM hyperscale data centre, Bukit Jalil

Being built
WhoEXSIM (developer); tenant a Japanese Fortune 500 company it does not name
WhereJalan Jalil Makmur, Bukit Jalil
StatusPhase 1 structure finished; first tenant (Aperia) cancelled in 2025; EXSIM says it has a new anchor tenant. Opening not announced
LandNot published
⚡ PowerNot published
💧 WaterNot published
CostNot published
⚠ Status is out of date (2025 reports).
⚠ Needs checking · Sources: EdgeProp (2025) · Baxtel (seen 2026-11-16)

MRCB data centre, Bukit Jalil

Announced (land or approval)
WhoMRCB (Bukit Jalil Sentral Property Sdn Bhd); to be leased to and run by Perintis Akal Sdn Bhd (PEMANDU Partners)
WhereBukit Jalil Sentral, Bukit Jalil
StatusAgreement signed Jun 2026; 10-year lease to the operator proposed
LandAbout 9.2 acres of MRCB's own leasehold land; building about 500,000 sq ft
⚡ Power65MW of computer load
💧 WaterNot published
CostAbout RM2.1b to build
Also running (smaller and telco data centres)
Checked and left out in Kuala Lumpur (1)
  • Smaller rooms named only on industry lists (KL): VADS Brickfields, TTDI and Semarak; Maxis Urban Data Centre (MRANTI); SAFEHOUSE; MyCloud (Exitra); Progenet; Exabytes (inside AIMS); EXSIM Cheras. Not yet confirmed from the operators. source

Negeri Sembilan5 confirmed

The newest hotspot, close to KLIA. Two big campuses are going up (Google at Springhill, Port Dickson, and Nexus Yang at Senawang), with Tera's 222 acres at Eco Business Park 7 next. Water: in Feb 2026 the Menteri Besar said the data centres use SAINS supply for now and that developers should build their own treatment plants from river or reclaimed water. Google is paying about RM651m for a 65-million-litre-a-day treatment plant and reservoir that also serve nearby homes. EcoWorld and NS Corp are studying a desalination plant (Nov 2026).

Nexus Yang Green Data Centre Campus

Being built
WhoVena Nexus (Vena Group)
WhereNS Semiconductor Valley (NSSV) Industrial Park, Senawang, Seremban
StatusGroundbreaking 26 Jan 2026 with the Menteri Besar. First phase due about Q1 2027 (industry report)
Land157 acres
⚡ PowerAbout 350MW of computer load to start
💧 WaterNot published
CostNot published

Google, Springhill Industrial Park

Being built
WhoPearl Computing Malaysia Sdn Bhd (Google); built by Gamuda
WhereSpringhill Industrial Park, Bandar Springhill / Lukut, Port Dickson
StatusBeing built. Earthworks under way since 2025; Gamuda won four data-centre building contracts in 2026 from a US technology company it does not name, due Q1 to Q4 2028
Land389 acres freehold, bought from Gamuda for RM455.2m (about RM27 psf), May 2025
⚡ PowerNot published by Google. Analysts estimate the land can take 700MW to 1,000MW. Jati Tinggi is building an interim 275kV supply for a data centre contractors call 'Gerbil' at Bandar Springhill
💧 WaterGamuda is building a 65-million-litre-a-day treatment plant (due Q2 2027) and an off-river reservoir (Q4 2028); Google is paying about RM651m. Both go to the state when finished and also serve nearby homes
CostBuilding contracts RM7.0b (Gamuda); enabling works RM1.01b
Gamuda's contracts don't name Google; the link is through the land sale to Pearl Computing. 'Gerbil' being part of this campus is not confirmed.

Green data centre by US investors, Nilai

Being built
WhoUS investors (not named)
WhereNilai
StatusBeing built (Menteri Besar, Apr 2025). Southern Score has a RM40m electrical job at a data centre in Nilai (Sep 2026)
LandNot published
⚡ PowerNot published
💧 WaterNot published
CostNot published
⚠ The owner is not named. The two sources may describe the same data centre.

Shinsei Malaysia 1

Being built
WhoRegal Orion Sdn Bhd (Japanese-owned)
WhereTechpark@Enstek, Labu
StatusBought about 70% built in 2018 for about RM66m; building restarted in 2022. Industry lists now call it running, but no opening has been announced
LandNot published
⚡ PowerNot published. Planned for 4,064 racks and 120,000 sq ft of hosting space
💧 WaterNot published
CostAbout RM1b planned
⚠ Whether it is running needs checking.
⚠ Needs checking · Sources: The Star (2020-11-28) · DCD (2020)

Tera Data Centers, Eco Business Park 7

Announced (land or approval)
WhoTera Data Centers (Malaysia) Sdn Bhd (Singapore-based)
WhereEco Business Park 7, Mukim Jimah, Port Dickson (Bukit Pelandok)
StatusConditional land deal signed 22 Sep 2026. Tera has not said what it will build
Land221.665 acres in two parcels, about RM1.013b (about RM105 psf), from the EcoWorld / SD Guthrie / NS Corp venture
⚡ PowerNot published
💧 WaterNot published. EcoWorld and NS Corp are studying a desalination plant for the park (Nov 2026)
CostNot published
✅ Confirmed · Sources: The Star (2026-09-22) · w.media (2026-09)
Checked and left out in Negeri Sembilan (4)
  • AWS 'KUL' sites in Cyberjaya, Bukit Jalil and Setul: Locations guessed by industry lists. AWS does not publish them. source
  • Tanco + China Mobile International, Port Dickson: MoU only (Jun 2026) to study a 50MW data centre; two years to sign a final agreement. source
  • NSSV AI data centre (Parcel F, Malaysia Vision Valley): Pre-development only; an Australian investor and a RM10b first phase have been mentioned, but no land deal or approval reported. source
  • Teliti Datacentre, Techpark@Enstek: Named only on industry lists; not yet confirmed from the operator. source

Penang4 confirmed

About 15MW running at Open DC PE2 (Bayan Lepas). Deep Source plans 67MW at Prai by mid-2027. No site publishes its water use. Since 1 July 2026 Penang charges data centres a separate water rate: RM5.31 per cubic metre (other businesses pay RM2.31 above 35 m³).

Open DC PE2

Running
WhoOpen DC Sdn Bhd (100% Extreme Broadband Sdn Bhd, Malaysian, private)
Where4, Medan Bayan Lepas, Bayan Lepas Technology Park, Penang island
StatusRunning since April 2025 (official launch Aug 2025). About 80% of the first 30MW is taken.
Land10-acre campus; a converted factory
⚡ PowerAbout 15MW switched on (Sep 2026). Built for 30MW; company target now 100MW
💧 WaterNot published. Cooled by air, chilled water and direct-to-chip; PUE under 1.5
CostNot published
Home of the Penang Internet Exchange (DE-CIX).

TM SJDC

Running
WhoTelekom Malaysia (TM Global)
WherePenang (TM: in the Penang Free Industrial Zone)
StatusRunning. One of TM's 6 main data centres
LandNot published
⚡ PowerNot published
💧 WaterNot published
CostNot published
TM's page names it but gives no size.
📍 Location not published

Deep Source AI data centre (former Southern Steel plant)

Being built
WhoDeep Source (PN) Sdn Bhd (Hong Kong-listed Deep Source Holdings, code 990)
WherePrai, Seberang Perai Tengah (Mukim 01)
StatusMITI approved it on 7 Sep 2026, with conditions on water and power. Early works started 1 Oct 2026. Still waiting for consent from the State and PDC on the tenancy
Land6.30 ha (15.6 acres), nine titles, rented from Southern Steel for 3 years at RM917,250 a month
⚡ Power67MW of computer load planned: 26MW by 31 Mar 2027, 41MW by 30 Jun 2027. An unnamed customer has signed a 10-year take-or-pay agreement for all 67MW
💧 WaterNot published (MITI approval has water conditions)
CostBuilder letter of intent US$221.1m (building + M&E; generators, cooling and power modules extra)
Checked and left out in Penang (5)
  • UVCell Solar + Iozela data centre complex: Partnership announced Dec 2024. No site, no size, no news since. source
  • VADS Bayan Baru and VADS Ipoh: Small rooms in Telekom exchange buildings, named only on industry lists. TM's own page doesn't list them. source
  • AIMS Penang (Suntech): Named on Baxtel, but AIMS's own website (checked 16 Nov 2026) no longer lists a Penang site. source
  • TM 'PG1', Jalan Sultan Ahmad Shah, George Town: Named only on industry lists. It may be the same as TM SJDC or a Telekom exchange room. source
  • CCH Holdings (Chicken Claypot House): A US$50m data centre services contract, not a building. source

Kedah2 confirmed

About 2MW running at Bukit Kayu Hitam (Open DC D8-1, growing to 4MW). AREA Group's campus in the same zone started building in Oct 2024, but there has been no news since. The Kulim plan was cancelled in May 2026. In Nov 2026 the state said Kulim Hi-Tech Park is for factories: it asked the park's operator to find other sites for two data-centre applications, naming Bakar Arang, Gurun, Bukit Kayu Hitam, Padang Terap and Padang Meha. No water figures published.

Open DC D8-1

Running
WhoOpen DC Sdn Bhd, built with Northern Gateway Sdn Bhd (owned by the Minister of Finance Inc)
WhereDelapan Special Border Economic Zone, Bukit Kayu Hitam
StatusRunning and almost full. Growing to 4MW, with a second block planned. Internet exchange to fully open end-2026 or Jan 2027
LandNot published
⚡ PowerAbout 2MW running, going to 4MW
💧 WaterNot published (uses solar power)
CostNot published
Data Center Map still calls it 'under construction'. The MD said in Sep 2026 that it is running at 2MW, so I used the newer statement.

AREA data centre campus

Being built
WhoData Gateway Sdn Bhd (AREA Group, private)
WhereDelapan Special Border Economic Zone, Bukit Kayu Hitam
StatusLand bought and building started Oct 2024. First data centre was due end-2025; no progress reported since
Land30 acres bought from Northern Gateway, with an option on 126 acres more (156 acres in all)
⚡ PowerNot published. Fed from a 132kV substation about 3 km away; TNB is building another main intake
💧 WaterNot published
CostWhole campus put at US$15b GDV
⚠ No progress news since Oct 2024 and the end-2025 date has passed. Status needs checking.
⚠ Needs checking · Sources: DCD (2024-10-18) · EdgeProp (2024-10)
Checked and left out in Kedah (2)
  • QEW Halal Industrial & DataTech Park: Heads of agreement only (Oct 2026). No data centre size, investor or tenant. source
  • GDC Kulim (KLM1) / Maxland: CANCELLED. Maxland's 60-year leases in Kulim Hi-Tech Park, 4.57 acres for the data centre and 4.854 acres for a district cooling plant (both RM50 psf), were revoked by deed on 14 May 2026. source

Perak1 confirmed

One being built: a 10.06MW data centre at Bagan Datuk (Privasia). MITI's condition is that it gets its own off-grid power, up to 50MW. Three other Perak plans are only studies or agreements so far (see the left-out list). No water figures published.

Silverstreams data centre

Being built
WhoSilver Streams Technofarm Sdn Bhd (wholly owned by Bursa-listed Privasia Technology Bhd)
WhereBagan Datuk
StatusBeing built. Builder Inspur appointed Dec 2025, contract signed Apr 2026, early works started. About 18 months to build
LandNot published
⚡ PowerPhase 1: 10.06MW of computer load. MITI approval (7 Sep 2026) requires its own off-grid renewable power, up to 50MW
💧 WaterNot published
CostBuild contract RM569m (Inspur Communication Malaysia)
Checked and left out in Perak (3)
  • NexQuantum NQ1, Ipoh area: Cahya Suria Services and China's Suzhou EnnoTHING, May 2026. 32MW first phase, about RM1b, part of up to 8 data centres. One report puts it in Silver Valley Technology Park. Still subject to planning and power approvals; no land deal reported. source
  • PKNPk + Global Vision Lab: Study of a 100MW-plus AI data centre. Only a non-disclosure agreement has been signed (Nov 2026); no site chosen yet. source
  • VADS Bayan Baru and VADS Ipoh: Small rooms in Telekom exchange buildings, named only on industry lists. TM's own page doesn't list them. source

Pahang1 confirmed

One announced: Deep Source has agreed to buy 435.6 acres in the Malaysia-China Kuantan Industrial Park. The state has picked Gebeng and Gambang as data-centre areas, saying both have enough water, power and fibre.

Deep Source AI data centres, MCKIP

Announced (land or approval)
WhoDeep Source (PN) Sdn Bhd (Hong Kong-listed Deep Source Holdings, code 990)
WherePN 33573, Lot 115524, Bandar Gebeng, Kuantan (Zone 2, Malaysia-China Kuantan Industrial Park)
StatusLand deal signed 18 Oct 2026; 10% paid. Needs State consent for a foreign-owned buyer (s.433B) and for the transfer. Plot 1 first (6–12 months to build after approvals), then 7 more plots
Land176.3 ha (435.6 acres), RM417.49m (RM22 psf), from ASAS Panorama (IJM Land 60%)
⚡ PowerNot published. Phase 2 includes its own power generation
💧 WaterNot published
CostNot published

Sarawak2 confirmed

One running (irix, the state's Tier IV data centre at Santubong), and one being built at FutureData Park, Kota Samarahan. The big SoftBank–Grab–PETROS plan is only a non-binding framework so far.

GDC Kuching (KCH1), FutureData Park

Being built
WhoGlobal Data Centre (GDC), in a building of the FutureData consortium (TSG Group of Sarawak and Cyclect of Singapore)
WhereJalan Kampung Tanjong Bako, Kota Samarahan
StatusFirst customer announced Oct 2024; industry lists say it is being built, due 2026
LandNot published
⚡ PowerGDC's data centre 17MW; the whole FutureData site was announced as 500MW
💧 WaterNot published
CostNot published
⚠ Building status needs checking.
Checked and left out in Sarawak (2)
  • SoftBank + Grab + PETROS, Kuching: Non-binding framework agreement (8 Oct 2026); Sarawak says part of a US$50b plan would likely go to Tanjung Embang, where a 405-hectare AI data campus site was identified. No land deal yet. source
  • MaNaDr Kuching and Bintulu: Planned AI data centres named only on industry lists. source

Perlis0 confirmed

None confirmed. The big Chuping plan (up to 1.25GW, off-grid) was announced in 2024–2025, but no land deal, approval or building has been reported since. It is on the left-out list.

No confirmed data centre yet.

Checked and left out in Perlis (1)
  • Bandar Teknologi Maju Perlis (PATP), Chuping: Joint venture of the Perlis State Secretary Inc and Sirage Skyvast. 600 acres; up to 1.25GW of AI data centres running off-grid (solar, batteries, gas); RM49b; first phase was aimed at mid-2027. Announced Nov 2024–Feb 2025. No land deal, approval or building reported since. source

Melaka0 confirmed

None confirmed yet. A Hong Kong firm (Victoria Data Centre) has said it wants to build a 96–100MW data centre in Jasin, worth over RM9b, and DPS Resources has signed several MoUs. None has a reported land deal or Data Centre Task Force approval yet (see the left-out list).

No confirmed data centre yet.

Checked and left out in Melaka (3)
  • Victoria Data Centre, Jasin: The Chief Minister said (Feb 2026) a Hong Kong firm intends to build three buildings of up to 96MW, worth over RM9b. No land deal or approval reported yet. source
  • DPS Resources + BBSB / Alibaba affiliate / China Energy unit: Non-binding MoUs (Apr–Aug 2026) for up to 89MW (400MW upside) on DPS's Lendu land; applications sent to the Data Centre Task Force but not approved yet. source
  • GDC Melaka (MLK1), DPS Bukit Rambai, DPS Alor Gajah: Named only on industry lists. source

Terengganu0 confirmed

No data centre found.

No confirmed data centre yet.

Kelantan0 confirmed

No data centre found.

No confirmed data centre yet.

Sabah0 confirmed

None confirmed. An AI data centre has been proposed at Kota Kinabalu Industrial Park (Nov 2026), and a Tier IV data centre near Kota Kinabalu was announced in 2023, but neither has a reported land deal, approval or opening.

No confirmed data centre yet.

Checked and left out in Sabah (2)
  • AI data centre at KKIP, Kota Kinabalu: A plan with state backing (Nov 2026); no land deal or approval reported. source
  • Poseidon Tier IV data centre, Aeropod, Kota Kinabalu: Announced 2023 (RM119m); no news of building or opening since. source

Labuan0 confirmed

Only a small Telekom room appears on industry lists (see the left-out list).

No confirmed data centre yet.

Checked and left out in Labuan (1)
  • VADS Labuan: A small room in a Telekom exchange, named only on industry lists. source

Where this comes from

  • Bursa and HKEX filings, company websites and press releases, and government answers in Parliament and the State Assemblies.
  • Industry lists (Data Center Map, Baxtel), used only to find names. A name needs a company source or a second source before it goes in; the rest are on the left-out lists.
  • News: The Star, Malay Mail, Bernama, NST, The Edge, EdgeProp, w.media, DCD, TechWire Asia, Utusan and others, plus our own stories.
  • Map pins come from Data Center Map, Google Maps and OpenStreetMap, and each one was checked on satellite pictures. A ring on the map means only the park or town is known.

Frequently Asked Questions

How many data centres are there in Malaysia?

This list has 72 data centres and campuses with a public source (20 November 2026): 27 running, 26 being built and 19 announced. TNB says it supplies 36 running data centres (March 2026). Some of those do not name themselves in public, so the two counts differ.

Which state has the most data centres?

Selangor and Johor have 25 each on this list (Selangor's mostly in Cyberjaya, plus new campuses in Puncak Alam, Serendah, Banting and Dengkil). Johor's are the biggest: about 3,700MW of the 5,850MW published nationwide.

How much electricity do data centres use in Malaysia?

The Energy Minister told Parliament that running data centres drew 1,102MW in April 2026, which is 54% of the 2,050MW approved for them. Approvals for all data-centre projects reached 12.3GW by August 2026. Data centres use about 7% of Malaysia's electricity in 2026, and the government expects up to 31% by 2035.

How much water do data centres use in Malaysia?

About half of what was approved for them: 51.4% of the 55.83 million litres a day approved for data centres (June 2026), or roughly 28.7 million litres a day. For the years 2025 to 2030, 445 million litres a day is approved for data-centre projects in Selangor, Johor and Negeri Sembilan; only 63.9 million of that is for data centres already running.

Are there data centres in Penang?

Yes. Open DC PE2 in Bayan Lepas has run since 2025, with about 15MW switched on and room for 30MW. Open DC PE1 and TM run smaller ones. Deep Source has MITI approval for a 67MW AI data centre at the old Southern Steel plant in Prai.

Where is Google building data centres in Malaysia?

Google runs its first Malaysian data centre at Elmina Business Park and is building a second phase there, a campus at Eco Business Park V in Puncak Alam (both Selangor) and one at Springhill Industrial Park near Port Dickson, Negeri Sembilan. Its company there is Pearl Computing Malaysia Sdn Bhd.

What does MW mean for a data centre?

MW (megawatts) is the size of the electricity load. Most companies quote the power for their computers (IT load). The power a site takes from TNB is higher, because cooling and other plant use electricity too. A 100MW data centre does not draw 100MW from day one; halls are filled over years.

Why are some data centres left out?

A project goes on this list only when land has been bought, an approval given, or the site is being built or running. MoUs, heads of agreement and studies with no land are on each State's "Checked and left out" list, with the reason and a source, so you can see what was checked.

Update log

  • 21 Nov 2026: Kedah: the state keeps Kulim Hi-Tech Park for factories and is steering two data-centre applications to other sites (our report).
  • 20 Nov 2026: ZDATA / Computility: added the probable land (38.5 acres bought from Tropicana), marked ⚠ until a source confirms it.
  • 20 Nov 2026: Added NTT DATA's planned 290MW campus on 68.5 acres in Gelang Patah, and Data Cloud Innovation's 18.4 acres in Nusa Cemerlang Industrial Park (bought from Crescendo for RM120m; Data Center Map calls it DAMAC Digital JHB01, so it leaves the "industry lists only" line).
  • 20 Nov 2026: Added DayOne's 65.3 acres in Tanjung Kupang, Iskandar Puteri, bought from Paragon Globe for RM398.1m, RM140 psf (our report).
  • 19 Nov 2026: Added the higher connected load charge for unused power (RM8.50 to RM89.64 per kW) to the official figures (our report).
  • 17 Nov 2026: Added Epoch Digital EMY1 in Nusa Cemerlang, Johor (120MW), now confirmed by Epoch and the AIIB; it had been on the "named only on industry lists" line (our report).
  • 17 Nov 2026: Page first published: 68 data centres in 9 States and Federal Territories, map, sortable table, and the official national power and water figures.