Kedah MB: Kulim Hi-Tech Park for factories, not data centres
- Kedah Menteri Besar Muhammad Sanusi Md Nor said on 18 November 2026 that Kulim Hi-Tech Park gives priority to factories, which create more jobs than data centres.
- Two companies have applied to build data centres in the park; the state asked Kulim Technology Park Corporation to find them other sites. Bakar Arang, Gurun, Bukit Kayu Hitam, Padang Terap and Padang Meha were named.
- Maxland cancelled its two 60-year KHTP leases for a data centre and a cooling plant in May 2026; both were priced at RM50 psf (our sum).
- In May Sanusi said an investor had wanted all 400 acres of KHTP Phase 5 for data centres, against up to 15,000 jobs if the land went to manufacturing.
Can data centres be built in Kulim Hi-Tech Park?
Kedah is not giving them priority there: on 18 November 2026 the state asked Kulim Technology Park Corporation to find other sites for two data-centre applications, keeping the park for factories.
Where does Kedah want data centres instead?
Menteri Besar Muhammad Sanusi Md Nor named Bakar Arang, Gurun, Bukit Kayu Hitam, Padang Terap and Padang Meha.
How much did Maxland pay to lease land in Kulim Hi-Tech Park?
RM9.95 million for 4.57 acres and RM10.57 million for 4.854 acres, both 60-year leases at about RM50 psf; both leases were cancelled on 14 May 2026.
Kedah will not give data centres priority at Kulim Hi-Tech Park (KHTP) and has asked the park's operator to find other sites for two companies that applied to build data centres there, Menteri Besar Datuk Seri Muhammad Sanusi Md Nor said on 18 November 2026. Land in the park goes first to factories, which create more jobs, he told the Kedah State Legislative Assembly, Bernama reported.
What he said
- Still open to data centres, but their use of land, water and electricity must be weighed before any approval. Sites must have enough power, water and land without hurting other users
- Jobs: a data centre typically creates about 100 jobs, fewer than factories
- The two applications: the state told Kulim Technology Park Corporation (KTPC), which runs the park, to find them other locations. The companies were not named
- Places he named instead: Bakar Arang, Gurun, Bukit Kayu Hitam, Padang Terap and Padang Meha. EdgeProp, citing Sinar Harian, reported that he also named the Kulim Industrial Corridor
The data centre that was cancelled
- The leases: Maxland Bhd's unit Maxland Data Sdn Bhd leased 4.57 acres from KTPC for a data centre on 5 December 2024, for RM9.95 million. Its sister unit Maxland Kool Sdn Bhd leased a further 4.854 acres for a district cooling plant on 31 January 2025, for RM10.57 million
- The land: both plots are part of GRN 199916, Lot 70480, Seksyen 39, Bandar Kulim, in Industrial Zone Phase 2, zoned industrial and vacant. Both leases ran for 60 years
- The price: both work out to RM50 psf for a 60-year lease, about RM2.18 million an acre (our sums)
- The end: on 14 May 2026 both units signed deeds with KTPC cancelling the leases. Maxland said the land no longer fitted its development plans
Phase 5: the bigger request
Commenting on Maxland's exit on 19 May 2026, Sanusi said one investor had wanted all 400 acres of KHTP Phase 5 for data centres, offering fewer than 1,000 jobs. Used for manufacturing, the same land could create up to 15,000 jobs, he said. He added that one data centre can use as much water as four factories (Utusan Malaysia).
Data centres in Kedah today
- Running: Open DC's data centre at Bukit Kayu Hitam, about 2MW and growing to 4MW
- Planned: AREA's campus in the same zone, where building started in October 2024 with no news since; and a halal and data technology park at Bukit Kayu Hitam that has a heads of agreement with Invest Kedah (our report)
- Elsewhere on Sanusi's list: Gurun has a heavy industrial park (our page), and Padang Meha is home to Kedah Rubber City (our report)
- Every site is on our list of data centres in Malaysia
- Bernama: Kedah favours industrial investments over data centres at KHTP - Sanusi (18 Nov 2026)
- Utusan Malaysia: Pusat data guna banyak air tapi peluang kerja terhad - Sanusi (19 May 2026)
- Maxland (Bursa): Lease agreement between Maxland Data Sdn Bhd and Kulim Technology Park Corporation Sdn Bhd (5 Dec 2024)
- Maxland (Bursa): Lease agreement between Maxland Kool Sdn Bhd and Kulim Technology Park Corporation Sdn Bhd (3 Feb 2025)
- Maxland (Bursa): Deed of revocation, Maxland Data Sdn Bhd lease (14 May 2026)
- Maxland (Bursa): Deed of revocation, Maxland Kool Sdn Bhd lease (14 May 2026)
- EdgeProp: Kedah seeks alternative sites for two Kulim data centre proposals (20 Nov 2026)
- EdgeProp: Maxland scraps land deals for data centre, district cooling system ventures in Kedah (15 May 2026)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
Aman Cove buys 69.95 acres in Kulim Hi-Tech Park for RM67m
Kedah developers Aman Setia and Imperio are buying 69.95 acres of township land inside KHTP from KTPC for RM67m, about RM22 psf, for a RM650m township.
LTAT reportedly picks Achi Jaya to buy Boustead Plantations
LTAT has reportedly chosen Achi Jaya to take over Boustead Plantations for about RM4.3b. BPlant owns about 13,800 acres of freehold estates in Kedah.
Bukit Kayu Hitam halal and data park gets Invest Kedah HoA
Invest Kedah signed three HoAs on 26 Oct, one for a proposed halal and data park in QEW Group's 258-acre park at Bukit Kayu Hitam, put at up to US$5b GDV.