11 Nov 2026 · Company News · 2 min read

Jati Tinggi wins RM33.1m 275kV link for Gerbil data centre

Jati Tinggi GroupPort DicksonData CentresInfrastructure
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • Jati Tinggi Holding accepted a RM33.1 million subcontract for interim 275kV power to the Gerbil data centre in Negeri Sembilan.
  • The work covers two 275kV cable circuits, a transition yard, an overhead line tap-off and secondary system changes, in nine months.
  • A May 2025 Advancecon filing places the Gerbil Data Centre at Bandar Springhill, Port Dickson, for Gamuda.
  • Jati Tinggi also won about RM142 million of 275kV work for a Banting Tech Park data centre in 2026.
Quick answers

What is the Gerbil data centre?

A data centre in Negeri Sembilan; a May 2025 Advancecon filing describes the Gerbil Data Centre at Bandar Springhill, Port Dickson, being built for Gamuda Bhd.

What did Jati Tinggi win in November 2026?

A RM33.1 million subcontract for interim 275kV power to the Gerbil data centre: two 275kV cable circuits, a transition yard and related works, over nine months.

Jati Tinggi Group Bhd's unit Jati Tinggi Holding Sdn Bhd has accepted a RM33.1 million subcontract to bring interim 275kV power to a data centre called Gerbil in Negeri Sembilan, it told Bursa Malaysia on 10 November 2026. The job is titled "Proposed 275kV bulk supply to a Gerbil data centre – interim supply".

The job

  • Work: design, supply, installation, testing and commissioning of two 275kV power cable circuits from a transition yard to the data centre's substation, building the transition yard, tapping off an overhead line, and related changes to secondary systems
  • Sum: RM33,097,596.66 at fixed rates, subject to re-measurement, before service tax
  • Time: nine months from the notice to start work, then a 12-month defect liability period
  • Payment: 40 days after each payment certificate, with 10% held back as retention
  • Client: a main contractor the filing does not name, described as a Malaysian electrical cable and infrastructure company with more than 20 years in construction
  • "Interim": the filing calls this an interim supply. It does not describe the permanent bulk supply arrangement or its timing

Where Gerbil is

  • Springhill, Port Dickson: Jati Tinggi's filing says only "Gerbil, Negeri Sembilan". In May 2025, Advancecon Holdings Bhd disclosed a RM47.5 million subcontract for the "Gerbil Data Centre at Bandar Springhill, Port Dickson", for Gamuda Bhd
  • The land: in May 2025, Google's land company, Pearl Computing, agreed to buy 389 acres in Springhill Industrial Park from a Gamuda unit (our report). Neither filing says whether Gerbil is part of that campus
  • Gamuda's pipeline there: since April 2026 Gamuda has won four Port Dickson data centre building contracts worth about RM7 billion from a US technology company it does not name, according to the same report

Its other data centre power jobs

Jati Tinggi has also won two 275kV jobs worth about RM142 million for a data centre campus at Banting Tech Park, Selangor, in August and September 2026 (our report).