EcoWorld, NS Corp to study desalination for industrial water
- EcoWorld and NS Corp will study a desalination plant as an extra source of industrial water for Eco Business Park 7 and future EcoWorld parks in Negeri Sembilan; the MoU runs for one year.
- No site, capacity, cost or water source has been given. It is a study, not a decision to build.
- EBP VII has sold about RM2 billion of land since November 2025, half of it in Tera Data Centers' RM1.013 billion purchase.
- The state and the federal government both want heavy water users such as data centres to rely less on public treated water.
What did EcoWorld and NS Corp sign?
A memorandum of understanding on 12 November 2026 to jointly study a desalination water treatment plant as an extra source of industrial water for EcoWorld's parks in Negeri Sembilan.
Which industrial park would the desalination plant serve?
Eco Business Park 7 in Port Dickson and any other industrial park EcoWorld develops in Negeri Sembilan; no site has been named for the plant.
How long does the EcoWorld–NS Corp MoU last?
One year, with an option to renew if both sides agree.
How much has Eco Business Park 7 sold?
About RM2 billion in less than a year since its launch in November 2025, according to EcoWorld.
On this page · 4 sections
Eco World Development Group Bhd (EcoWorld) signed a memorandum of understanding with NS Corporation (NS Corp) on Thursday, 12 November 2026, to study a desalination water treatment plant in Negeri Sembilan. The plant would be an extra source of industrial water for EcoWorld's industrial parks in the state, starting with Eco Business Park 7 (EBP VII) in Port Dickson. EcoWorld president and chief executive Dato' Seri Chang Khim Wah and NS Corp chief executive Datuk Norazhar Musa attended the signing.
What the MoU covers
- Who: EcoWorld and NS Corp, the state statutory body that promotes and coordinates investment in Negeri Sembilan, including the Malaysia Vision Valley 2.0 (MVV 2.0) corridor
- What: joint feasibility studies on a desalination water treatment plant as an "alternative and supplementary" source of industrial water
- Where: EBP VII and any other industrial park EcoWorld develops in Negeri Sembilan in future
- How long: one year, with an option to renew if both sides agree
- Not given: the plant's site, capacity, cost, or the water it would treat
This is a study, not a decision to build. EcoWorld announced it in a press statement; it has not filed the MoU with Bursa Malaysia.
Why EBP VII needs the water
EcoWorld says EBP VII has sold about RM2 billion of land in less than a year since its launch in November 2025, and enquiries from local and foreign investors continue. The biggest sale so far is Tera Data Centers' RM1.013 billion purchase of 221.665 acres, about RM105 psf, in September (our report). That one deal is about half of the RM2 billion.
The park covers 1,195 freehold acres in Mukim Jimah, Port Dickson, in Parcel C of MVV 2.0. It is owned 55:30:15 by EcoWorld, SD Guthrie and NS Corp.
Negeri Sembilan approved RM41.5 billion of investments from 2023 to June 2026, EcoWorld said: RM24.2 billion (58%) domestic and RM17.3 billion (42%) foreign, most of it in MVV 2.0.
Water for Port Dickson's factories and data centres
- The state, February 2026: Menteri Besar Datuk Seri Aminuddin Harun said the three data centres planned in Seremban and Port Dickson would use Syarikat Air Negeri Sembilan (SAINS) supply for now, as the state has enough spare treated water. He said the state was also planning new industrial water, including recycled "new water", and that data-centre developers are expected to build their own treatment plants using river water or reclaimed water from IWK sewage plants. He spoke at the opening of the Ngoi-Ngoi Phase 2 water treatment plant, which produces 150 million litres a day (MLD).
- Google, November 2026: Google committed US$160 million (about RM651 million) to an off-river storage reservoir and a 65 MLD water treatment plant built by Gamuda. It will serve local communities and Google's Springhill campus in Port Dickson (our report).
- Federal government, August 2026: the Ministry of Energy Transition and Water Transformation (PETRA) said treated water should be kept for homes first. It wants heavy users to turn to reclaimed water, desalination and other sources. Before desalination is used widely, it said, location, energy needs, production cost and economic viability must be weighed. Four reclaimed-water plants in Peninsular Malaysia already supply data centres, with a combined 19.5 MLD.
- Other states: Selangor is studying a seawater desalination plant of about 300 MLD and has two sites proposed (April 2026). Penang's water operator PBAPP wants desalination projects in the 2030s and says the cost is "significantly higher" than treating river water (September 2026).
Update, 18 November 2026
- Johor too: on 16 November EcoWorld signed a collaboration with Permodalan Darul Ta'zim (PDT), the Johor state investment arm, to explore selling renewable electricity and reclaimed water as one package to data centres and factories in its QUANTUM and Eco Business Parks. Power and renewable energy certificates would come from PDT Energy Sdn Bhd and its partners under the Corporate Renewable Energy Supply Scheme (our report on the scheme), and Johor Special Water Sdn Bhd, the state's sole industrial water supplier, would supply raw, treated-effluent and reclaimed water, The Star reported
- Not settled yet: prices and terms are left to a later supply agreement, and no volumes or dates were given
Cover photo: Eco World Development Group, via EdgeProp.
- New Straits Times — “Eco World, NS Corp to explore water desalination plant in Negeri Sembilan” (12 Nov 2026)
- EdgeProp — “EcoWorld, NS Corp to study desalination for industrial parks” (13 Nov 2026)
- Utusan Malaysia — “Pusat data: Negeri Sembilan bangunkan bekalan air industri” (20 Feb 2026)
- Bernama — “Govt Eyes Seawater Desalination To Support Industrial Needs - PETRA” (4 Aug 2026)
- Free Malaysia Today — “Selangor mulls seawater desalination plant” (22 Apr 2026)
- The Star — “PBAPP moots desalination projects to safeguard against future water shortages” (23 Sep 2026)
- The Star: EcoWorld, PDT partner to supply green utilities to Johor industrial and data centre parks (16 Nov 2026)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
Tera buys 222 acres at Eco Business Park 7 for RM1.01b
Tera Data Centers is paying RM1.013 billion, about RM105 psf, for 221.665 acres in Eco Business Park 7, Port Dickson, next to Google’s campus. The EcoWorld–SD Guthrie–NS Corp ventu…
Google's US$15b plan: Puncak Alam, Serendah, Port Dickson
Google will invest US$15b in Malaysia in 2027–28 and plans three new campuses. Bursa filings show who holds its land: Pearl Computing Malaysia Sdn Bhd.
Southern Score wins RM146.8m Port Dickson data centre jobs
Southern Score Builders' unit SJEE signed two electrical subcontracts worth RM146.8m on 11 Nov 2026 for two data centres in Port Dickson, due by April 2028.