Teladan books RM283m sales; Jasin industrial parks next
- Teladan Group sold RM283.38 million of property in the nine months to September 2026 and had RM317.28 million of unbilled sales; revenue rose 25.8% to RM270.69 million and profit after tax 34% to RM27.09 million.
- Its German Technology Park is a 418.63-acre managed industrial park in Mukim Ayer Panas, Jasin. Teladan's unit Riverwell Resources develops the 121.7-acre Phase 1; Jakel Group and Franky Land develop the 296.91-acre Phase 2.
- Phase 1 plots of one to three acres were priced at about RM60 psf in February 2026; Riverwell bought the land in 2021 at about RM8 psf (our sum).
- The Golden Valley Industrial Hub, 270 acres in Jasin, is still at the memorandum stage; its landowner, prices and timetable have not been published.
Where is the German Technology Park in Melaka?
In Mukim Ayer Panas, Jasin district, reached through the Ayer Keroh and Jasin interchanges; it is a 418.63-acre park in two phases.
How much are plots in the German Technology Park?
About RM60 psf for plots of one to three acres in Phase 1, EdgeProp reported in February 2026.
What is the Golden Valley Industrial Hub?
A planned 270-acre industrial hub in Jasin, Melaka, for which Teladan signed a memorandum with Gezhouba Engineering (Malaysia) and Nanyang Sea Silk Road in March 2025.
How much property did Teladan sell in 2026?
RM283.38 million in the nine months to 30 September 2026, with RM317.28 million of unbilled sales at that date.
Teladan Group Bhd, a Melaka property developer, sold RM283.38 million of property in the nine months to September 2026 and had RM317.28 million of unbilled sales at the end of the period, its Bursa Malaysia filing on 18 November shows. It named two industrial projects in Melaka's Jasin district as the next step for its business: the German Technology Park, already selling and being billed, and the planned Golden Valley Industrial Hub.
The results
| Nine months to 30 September | 2026 | 2025 |
|---|---|---|
| Revenue | RM270.69m | RM215.16m |
| Profit after tax | RM27.09m | RM20.21m |
| Profit attributable to shareholders | RM26.76m | RM20.21m |
| Gross profit margin | 22.5% | 22.6% |
- The July–September quarter: revenue RM86.10 million and profit after tax RM7.42 million; the gross margin slipped to 21.3%, from the quarter before
- What drove it: Taman Bertam Heights Phase 2A2, Taman Gapam Perdana Phase 1B, the German Technology Park, Taman Desa Bertam Phase 1A and Pusat Komersial Bukit Intan in Seremban
- Land bank: about 643.6 acres with an estimated GDV of RM2.0 billion, the company said
German Technology Park
- Where: Mukim Ayer Panas, Jasin district, reached through the Ayer Keroh and Jasin interchanges of the North–South Expressway
- Size: a 418.63-acre park in two phases. Phase 1, 121.7 acres, is Teladan's, through its unit Riverwell Resources Sdn Bhd; Phase 2, 296.91 acres, is being developed by Jakel Group and Franky Land Sdn Bhd, EdgeProp reported
- The land: two leasehold titles, PN 30156 Lot 4674 and PN 71013 Lot 14719, 49.26 hectares in all, leased to 15 August 2094
- What is built: Phase 1 has 45 terrace factories, 64 semi-detached factories, a central workers' quarters and 22 industrial plots of one to three acres priced at about RM60 psf. Chief executive Allan Ngu said 50% to 60% of the factories were taken up, mostly by local buyers (EdgeProp, February 2026)
- Selling the plots: on 6 February 2026 Riverwell appointed Melaka Corporation (MCorp), the State development agency, as sole agent for the 22 plots for three years. MCorp keeps any amount above an agreed base price. Riverwell pays for the roads and services, and the first phase is due within three years
- The plan: Melaka's first managed industrial park, aimed at German manufacturers and their suppliers
Our numbers
- Riverwell bought these two lots with three others, 136.916 hectares (338 acres) in all, from Bakat Muhibbah Sdn Bhd in September 2021 for RM117.9 million, about RM8 psf. In that filing both lots were marked for residential use only; the 2026 agreement calls the plots industrial land
- At end-2025 the park's 121.72 acres stood in Teladan's books at RM68.97 million, about RM13 psf, including costs spent so far
- At RM60 psf, a one-acre plot costs about RM2.6 million and a three-acre plot about RM7.8 million
Golden Valley Industrial Hub
- Size and place: 270 acres (109.26 hectares) in Jasin, about 16.6km from the Ayer Keroh toll plaza, its chairman Datuk Wira Gan Tian Loo said in March 2025 (The Star). Teladan's managing director placed it in Durian Tunggal
- The partners: a memorandum signed on 21 March 2025 with Gezhouba Engineering (Malaysia) Sdn Bhd, which would study and build a central waste-water plant and green-energy supply, and Nanyang Sea Silk Road Sdn Bhd, which would supply local materials. Teladan handles State support, land conversion and funding
- Not yet known: who owns the land, plot sizes, prices and a timetable. The memorandum ran for one year, and Teladan has not announced an extension on Bursa
- Teladan Group (Bursa): Quarterly report for the period ended 30 September 2026 (18 Nov 2026)
- Teladan Group (Bursa): Press release, Teladan records 34.0% PAT growth in 9MFY2026 (18 Nov 2026)
- Teladan Group (Bursa): Strategic co-operation agreement between Riverwell Resources Sdn Bhd and Melaka Corporation (6 Feb 2026)
- Teladan Group (Bursa): Memorandum of understanding with Gezhouba Engineering (Malaysia) and Nanyang Sea Silk Road for the Golden Valley Industrial Hub (21 Mar 2025)
- Teladan Group (Bursa): Annual Report 2025 (30 Apr 2026)
- Teladan Setia Group (Bursa): Proposed acquisition of 5 parcels of leasehold land in Mukim Ayer Panas, Jasin (6 Sep 2021)
- EdgeProp: MCorp, Teladan Group jointly launch Phase 1 of German Technology Park, Melaka (9 Feb 2026)
- The Star: Teladan Group inks MoU to develop industrial hub (24 Mar 2025)
- EdgeProp: Teladan's nine-month net profit rises 32% on higher project billings (19 Nov 2026)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
UPA builds 13 semi-D factories in Seri Kembangan, GDV RM94m
Stationery maker UPA Corporation is turning 3.03 acres it has held since 1994 in Bukit Serdang, Seri Kembangan, into 13 semi-D factories worth RM94.1m.
Kitacon to build 14 detached factories in Elmina, RM54.9m
Kitacon will build 14 two-storey detached factories, a switch station and two substations for Sime Darby Property in Taman Perdagangan Elmina, Rawang, by 2028.