Kitacon to build 14 detached factories in Elmina, RM54.9m
- Kitacon won a RM54.872 million contract from Sime Darby Property (Elmina North) to build 14 two-storey detached factories.
- The site is Taman Perdagangan Elmina, Mukim Rawang, Gombak, with one main switch station and two substations.
- Work runs 22 months from 30 November 2026, to about September 2028.
- Sime Darby Property's last detached factories in Elmina, in 2022, sold at RM8.38 million each for 11,942 sq ft.
Who is building Sime Darby Property's new detached factories in Elmina?
Kitacon Sdn Bhd, a unit of Kumpulan Kitacon Bhd, under a RM54.872 million contract accepted on 7 November 2026.
How many factories are in Elmina Phase i25?
Fourteen two-storey detached factories: 10 of Type A, 2 of Type B and 2 of Type C, plus a main switch station and two substations.
When will the Elmina Phase i25 factories be completed?
Work starts on 30 November 2026 and runs 22 months, to about September 2028.
Kumpulan Kitacon Bhd's unit Kitacon Sdn Bhd has won a RM54.872 million contract from Sime Darby Property (Elmina North) Sdn Bhd to build 14 two-storey detached factories in Taman Perdagangan Elmina, Mukim Rawang, Gombak, Selangor. It accepted the letter of award on 7 November 2026 and told Bursa Malaysia on 10 November.
The job
- Phase i25: 10 detached factories of Type A, 2 of Type B and 2 of Type C, all two storeys, each group with a refuse chamber and an electric vehicle charging bay
- Power: one main switch station and two distribution substations
- Timing: from 30 November 2026, for 22 months, so done by about September 2028
- Not given: the factory sizes, the land area and the selling prices
Sime Darby Property's Elmina factories
- Elmina Business Park: about 1,500 acres of freehold industrial land, which Sime Darby Property calls the Klang Valley's largest freehold industrial park
- Elmina Business Park 2: 600 acres about 2km to the north in Rawang, with a planned sales value of RM1.72 billion, 72 semi-detached factories and industrial lots of 2 to 4 acres. Its first 19 lots, launched in January 2026, were about 70% taken up by April, EdgeProp reported
- The last detached factories: in September 2022, four detached factories on 120ft by 215ft lots, with 11,942 sq ft of built-up area, were launched at RM8.38 million each and fully taken up. That is about RM702 per sq ft of built-up area (our calculation)
- Which park: the filing does not say whether Phase i25 is in the first or the second business park
Kitacon's other 2026 jobs
- March: RM89 million for 258 two-storey terraces at Bandar Tasik Puteri, Rawang, for Rawang Lakes Sdn Bhd
- March: RM99.28 million for 147 strata terraces at Cyberjaya, for ParkCity Botanika Sdn Bhd
- Together with this job: about RM243.2 million announced this year (our sum)
- Bursa Malaysia — Kumpulan Kitacon: letter of award of main building works, RM54.872m, from Sime Darby Property (Elmina North) (10 Nov 2026)
- Bursa Malaysia — Kumpulan Kitacon: letter of award, RM99.28m, from ParkCity Botanika (25 Mar 2026)
- Bursa Malaysia — Kumpulan Kitacon: letter of award, RM89m, from Rawang Lakes (10 Mar 2026)
- EdgeProp — Sime Darby Property launches industrial lots and factories at Elmina Business Park 2 (13 Apr 2026)
- EdgeProp — SDP's Detached Factories 1 and Twin Factories 3 in Elmina Business Park fully taken up (26 Sep 2022)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
SD Guthrie sells 264 acres in Byram, Penang, for RM252.6m
SD Guthrie is selling 263.63 acres of its Byram estate to Nexis X for RM252.64m, one of three land sales RHB expects it to book in the last quarter of 2026.
Sime Darby Property eyes REIT by 2028, 1,022-acre BBR North
Sime Darby Property is weighing an industrial and data centre REIT by 2028 and plans a 1,021.93-acre heavy industrial park in Kuala Selangor with SD Guthrie.
Carey Island: Selangor’s third port and industrial hub
Carey Island is set to host Port Klang’s third terminal and a port-industrial zone on SD Guthrie land. As of Oct 2026, Selangor awaits the port licence.