24 Nov 2026 · Company News · 3 min read

iCents wins RM85.7m of data centre and wafer plant jobs

iCents Group Holdings BerhadSelangorIndonesiaData CentresSemiconductors
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • iCents Group accepted three jobs worth RM85.7 million on 23 November 2026; the clients and data-centre sites are not named.
  • The largest is a RM65.1 million air-conditioning and ventilation subcontract for a data centre, due in January 2028.
  • RM15.1 million is Stage 2 of a semiconductor wafer plant in Selangor for the Malaysian unit of a US company, making RM36.15 million with Stage 1.
  • Of the RM204.6 million of contracts iCents has announced in 2026, 72% is data-centre work (our sums).
Quick answers

What contracts did iCents win in November 2026?

Three jobs worth RM85.7 million: RM65.1 million of data-centre air-conditioning, RM15.1 million for a wafer plant in Selangor and RM5.5 million of data-centre ceilings in Indonesia.

Where is the iCents data-centre job?

iCents has not disclosed the site or the client; it is a subcontract from a local construction company, due in January 2028.

Where is the semiconductor wafer plant iCents is building?

In Selangor, for the Malaysian subsidiary of a US semiconductor technology company; the two stages total RM36.15 million.

Where is iCents' factory?

It owns a freehold factory in the College Heights light industrial area in Mantin, Negeri Sembilan, with 20,756 sq ft of built-up area.

iCents Group Holdings Bhd, a cleanroom and building-services contractor listed on the ACE Market, said on 23 November 2026 that its subsidiaries had accepted three jobs worth RM85.7 million in total. The largest is a RM65.1 million air-conditioning and ventilation subcontract for a data centre. The filings do not name the clients or the data-centre sites. The wafer plant, though, is in Selangor, according to iCents' filing of 12 October.

The three jobs

  • RM65.12 million (including SST), data centre: VC Engineering Sdn Bhd will supply, install, test, commission and maintain the air-conditioning and mechanical ventilation system for a data-centre project, as a subcontractor to a local construction company. It is due on 14 January 2028.
  • RM15.10 million (excluding SST), wafer plant: VC Engineering will carry out Stage 2 of a turnkey semiconductor wafer processing facility in Selangor for the Malaysian subsidiary of a US semiconductor technology company. This stage covers the rest of Phase 1, including the plant's mechanical, utility and electrical systems, and is due on 16 June 2027. Stage 1, worth RM21.05 million, was awarded on 12 October, so the two stages total RM36.15 million.
  • RM5.47 million (Rp24.21 billion), Indonesia: Maytech Cleanroom Manufacturing Sdn Bhd will design, supply and deliver a heavy-duty walkable ceiling system for a data-centre development, for an Indonesian construction and steel-trading company. It is due on 22 February 2027.

Two of the three jobs are for data centres, including the one in Indonesia.

Its contracts this year

iCents has announced RM204.6 million of contracts on Bursa Malaysia in 2026, and RM146.4 million of that (72%) is data-centre work (our sums). Earlier this year it won:

  • January: RM9.12 million for an industrial manufacturing facility.
  • February: RM20.26 million for air-conditioning at two data centres.
  • March: RM14.1 million for data-centre systems in Indonesia.
  • May: RM34.5 million for air-conditioning at a data centre.
  • June: RM6.95 million for data-centre supplies in Indonesia.
  • July: RM12.9 million to renovate a factory, warehouse and office in the Klang Valley for the Malaysian unit of a Netherlands-based technology company.

The RM85.7 million announced on 23 November equals 80% of its revenue for the year to June 2026 (our sums).

The company and its property

  • Results: revenue rose 31.5% to RM107.22 million in the year to June 2026. Profit after tax fell to RM4.31 million, from RM7.98 million, after a one-off RM5.1 million margin adjustment when it closed out a semiconductor contract.
  • Orders: at end-June it held an order book of about RM63 million, plus about RM70 million of projects already started. It is targeting an order book of about RM100 million by the end of 2026 and is bidding on about RM800 million of work, roughly half data centres and 40% semiconductors.
  • Factory: it owns a freehold factory at No. 24, Jalan CH Light Industries 1, College Heights light industrial area, Mantin, Negeri Sembilan (Geran 198706, Lot 19884). It has 20,756 sq ft of built-up area on 42,754 sq ft of land, was bought in July 2020 and has a book value of RM6.57 million.
  • Land: it also owns 66,455 sq ft (1.53 acres) of vacant freehold industrial land at Lot 09, Bandar Springhill Industrial Park, Port Dickson (HS(D) 45124, PT 2165), bought in May 2023. Its book value is RM2.09 million, about RM31.5 per sq ft (our sums).
  • New plant: in April 2026 Maytech opened a new manufacturing facility in Mantin, investing about RM15 million and creating about 100 jobs. Its IPO budget lists rent for that facility.
  • Penang: in the year to June 2026 it completed a cleanroom system for a semiconductor plant in Penang; the client is not named.

Ir. Ts. Vincent Ong Mum Fei is managing director, and iCents listed on 17 July 2025.

Need help with your factory, plant or industrial land?

Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.