Home› News› Kedah
25 Nov 2026 · Investment · 2 min read

HLGY leases 300 acres in Kedah Rubber City for solar farm

HLGY Energy Sdn BhdNorthern Corridor Implementation Authority (NCIA)KedahPadang TerapRenewable EnergyIndustrial Parks
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • HLGY Energy Sdn Bhd is building a solar power plant on about 300 acres of Kedah Rubber City, Padang Terap, on land held through NCIA for 28 years; the rent has not been disclosed.
  • The plant has about 120MW of solar panels and about 240MWh of battery storage, a gross development value of nearly RM500 million and a June 2028 completion target.
  • Bridge Data Centres Malaysia IV Sdn Bhd is the sole buyer of the power for now, under the Corporate Renewable Energy Supply Scheme (CRESS).
  • The solar farm takes about a quarter of the roughly 1,250-acre park (our sums); NCIA said construction started in November 2026.
Quick answers

How much land is HLGY Energy using in Kedah Rubber City?

About 300 acres, on land secured through NCIA under a lease arrangement that runs for 28 years. That is about a quarter of the roughly 1,250-acre park.

Who will buy the power from HLGY's Kedah Rubber City solar plant?

Bridge Data Centres Malaysia IV Sdn Bhd is the sole buyer for now, with the electricity delivered over the national grid under CRESS.

When will HLGY's Kedah solar plant be completed?

HLGY targets completion in June 2028. NCIA said on 20 November 2026 that construction had started.

What is CRESS?

The Corporate Renewable Energy Supply Scheme, introduced in September 2024, lets a company buy renewable electricity directly from a developer, delivered over the national grid.

HLGY Energy Sdn Bhd is building a RM500 million solar power plant on about 300 acres of Kedah Rubber City (KRC) in Padang Terap, Kedah, on land it holds through the Northern Corridor Implementation Authority (NCIA) for 28 years. The company gave the details at a partnership signing on 17 November 2026, and NCIA said on 20 November that construction had started. NCIA calls it Malaysia's first project under the Corporate Renewable Energy Supply Scheme (CRESS) to start building.

The land

  • Where: Kedah Rubber City, the park in Padang Terap set aside for rubber-product factories. The park sits on Federal Lands Commissioner land leased to NCIA (our report).
  • Size and term: about 300 acres, on a lease arrangement that runs for 28 years, secured through NCIA. The rent has not been disclosed.
  • Share of the park: about a quarter of KRC's roughly 1,250 acres (our sums). Prinx Tire's tyre plant, the park's anchor, takes 102.63 acres.

The plant

  • Size: about 120MW of solar panels with about 240MWh of battery storage, generating about 224 gigawatt-hours a year.
  • Value: gross development value of nearly RM500 million, backed by a RM360 million term loan from AmBank Islamic.
  • Timing: completion targeted for June 2028. HLGY says Tenaga Nasional has approved both stages of its power system study.

Who buys the power

  • Buyer: Bridge Data Centres Malaysia IV Sdn Bhd, a data-centre company, is the sole buyer for now.
  • How: under CRESS, introduced in September 2024, a company can buy renewable electricity directly from a developer, delivered over the national grid.
  • Other partners: Mabcon Energy, U Mobile (private 5G and AI for running the plant) and Asia CarbonX Change (renewable energy certificates).

What comes next

  • HLGY chairman Kenneth Yap Kian Hoong said the company is looking at more renewable energy projects in KRC with NCIA.
  • NCIA said its renewable energy zone for the corridor, SREEZ@NCER, is expected to extend to the Chuping Valley Industrial Area in Perlis and the Kedah Science & Technology Park in Bukit Kayu Hitam.

For comparison, Pekat Group agreed in September to lease about 470 acres of oil palm land in Sungai Petani for 24 years for a solar and battery plant, at RM350 an acre a month (our report).

📰 Sources: first reported by The Edge: HLGY eyes more renewable energy projects in Kedah Rubber City (17 Nov 2026) and DagangNews: Projek solar CRESS pertama Malaysia bernilai RM500 juta mula dibina di Kedah Rubber City (NCIA statement) (20 Nov 2026). Facts summarised in our own words, with our own analysis added.
Need help with your factory, plant or industrial land?

Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.

Related news