MRT3 to link Pantai Dalam, Klang Lama and Kuchai by 2032
- MRT Corp's station list puts Pantai Dalam (KTM Komuter), Jalan Klang Lama and Kuchai (MRT Putrajaya Line) next to each other on MRT3; one rail route between Pantai Dalam and Kuchai today takes three lines and two changes.
- MRT3 got final approval on 17 July 2025 with 690 land lots to acquire; MRT Corp aims to finish acquisition by end-2026, start construction in 2027 and run trains in 2032.
- IJM Land plans a 300-metre bridge from Pantai Sentral Park to the Pantai Dalam station, and DBKL is studying a Bazaria Pantai redevelopment with MRT3 in mind; neither has a confirmed approval or date.
Which MRT3 stations are near Pantai Dalam and Old Klang Road?
MRT Corp's list has Pantai Dalam (connecting with KTM Komuter), Jalan Klang Lama and Kuchai (connecting with the MRT Putrajaya Line) in a row, between Pantai Permai and Salak Jaya.
When will the MRT3 Circle Line open?
MRT Corp aims to start construction in 2027 and begin full operations in 2032, after land acquisition, which it plans to finish by the end of 2026.
Will Pantai Sentral Park be linked to the MRT3 station?
IJM Land said in May 2025 it would build a 300-metre bridge to the future Pantai Dalam station; its approval and timing have not been confirmed.
The MRT3 Circle Line would put Pantai Dalam, Jalan Klang Lama and Kuchai in Kuala Lumpur on one rail line, an EdgeProp analysis pointed out on 16 November 2026. Pantai Dalam already has a KTM Komuter station. MRT3 would add a direct line from there past Old Klang Road to Kuchai, where it meets the MRT Putrajaya Line. MRT Corp aims to start construction in 2027 and run trains from 2032.
The stretch
- Stations: MRT Corp's December 2025 report lists Universiti, Pantai Permai, Pantai Dalam, Jalan Klang Lama, Kuchai and Salak Jaya in that order. The names are working names and can still change
- Interchanges: Pantai Dalam connects with KTM Komuter, and Kuchai with the MRT Putrajaya Line
- Today: one rail route from Pantai Dalam to Kuchai, as EdgeProp laid it out, takes KTM Komuter to Abdullah Hukum, the LRT Kelana Jaya Line to Ampang Park and the MRT Putrajaya Line to Kuchai: three lines and two changes. On MRT3 it would be one line with one stop, Jalan Klang Lama, in between. No journey time has been published
Where MRT3 stands
- 17 July 2025: Transport Minister Loke Siew Fook signed the Final Railway Scheme. The land lots to be acquired were cut from 1,012 to 690
- The line: 51.6 km, 33 stations (26 elevated, 7 underground), 10 interchange points, 2 depots and 11 park-and-ride sites, according to MRT Corp
- Land: notices under Section 8 of the Land Acquisition Act 1960 were gazetted at the end of July 2025 for Selangor and in August 2025 for Kuala Lumpur. MRT Corp aims to finish acquiring the land by the end of 2026
- 29 June 2026: MRT Corp invited contractors to express interest in protecting and maintaining land along the MRT3 line. As of 17 November 2026 its tender list shows no tender for the main construction works
Around Pantai Dalam
- Pantai Sentral Park: IJM Land's 58-acre township, with a gross development value of RM8.3 billion. In May 2025 IJM Land said it would build a 300-metre bridge from the township's urban park to the future Pantai Dalam station. IJM's 2026 annual report still calls the bridge proposed, and EdgeProp said its approval and delivery have not been confirmed
- Enlace @ Pantai Sentral Park: IJM Land's RM3.9 billion mixed-use project of serviced apartments, offices, shops and a healthcare centre. EdgeProp reported memoranda of understanding with 16 tenants for its Enlace Shoppes in July 2025
- Bazaria Pantai: on 8 March 2026, Communications Minister and Lembah Pantai MP Fahmi Fadzil said Kuala Lumpur City Hall (DBKL) was studying a redevelopment of the 13- to 14-year-old hawker premises. Two designs were being looked at: an open layout, or a multi-storey building with a one-stop centre, a car park and larger stalls. The nearby MRT3 line is being taken into account, and the final decision needs talks with MRT Corp. No decision has been reported since
- Home prices: EdgeProp's project pages showed median transacted prices of RM779 psf at Inwood Residences and RM830 psf at Secoya Residences over the 48 months to 14 November 2026. These figures do not show any MRT3 premium
Land along Jalan Kuchai Lama
Two large land deals were struck on Jalan Kuchai Lama this year, near the Kuchai end of the stretch:
- July 2026: Ajinomoto (Malaysia) agreed to sell its old office and factory site, 10.51 hectares (about 26 acres) of leasehold land, to Paragon TSL Sdn Bhd for RM408 million, about RM361 psf (our report)
- September 2026: AYER Holdings agreed to buy 9.11 freehold acres for RM138 million, about RM348 psf. Its filing describes the land as near the Kuchai Lama MRT station (our report)
What the KL Local Plan allows
The Kuala Lumpur Local Plan 2040, gazetted on 28 May 2025, offers four kinds of extra plot ratio: in Transit Planning Zones and Transit Influence Zones, for lot amalgamation, in special redevelopment areas, and for projects with affordable homes. Whether a lot qualifies, and how much more it may build, depends on the plan's development control rules and DBKL's assessment of the site.
- EdgeProp: Pantai Dalam already has rail. What would MRT3 change? (16 Nov 2026)
- MRT Corp: MRT3 Circle Line Railway Scheme receives final approval (media release) (17 Jul 2025)
- MRT Corp: Stakeholder Management Report, Circle Line (MRT3) Public Inspection (2025-12)
- MRT Corp: tender list (EOIs for land along MRT3, 29 Jun 2026) (seen 2026-11-17)
- IJM Land: IJM Land and Amona Group break ground on Urban Park at Pantai Sentral Park (26 May 2025)
- Berita RTM: Klinik kesihatan baharu di Lembah Pantai (incl. Bazaria Pantai) (8 Mar 2026)
- DBKL: Pelan Tempatan Kuala Lumpur 2040, Jilid 1 Bahagian 2 (Peta Zon Guna Tanah) (28 May 2025)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
Nexus Sedenak eyes inland port, RM12b of investment in Kulai
Kulai MP Teo Nie Ching says the 2,940-acre Nexus Sedenak may become an inland port; Budget 2027 puts its potential at RM12b of investment and 45,000 jobs.
Penang LRT: first package 15.5% done, RM397m to local firms
The KOMTAR–Silicon Island stretch of the Mutiara LRT was 15.5% done in September; the RM2.69b sea crossing was then awarded and the line hit 16%.
Penang Silicon Island: 480 acres reclaimed, RM1.9 billion spent, LRT depot handed over
Our standing page on Penang Silicon Island: 480 of 2,300 acres reclaimed, RM14 billion cost, first industrial land sale early 2027, first factories early 2029.