Johor plans 20 flood projects worth RM35.36m in Johor Bahru
- Johor is funding 20 flood mitigation projects worth RM35.36 million in Johor Bahru across six river basins.
- Four projects worth RM8.5 million in the Sungai Chat basin deepen two ponds and build two new ones by September 2027.
- The works add retention ponds, drains, culverts, pumps and floodgates after flash floods hit 12 areas of the city.
- MBJB will fine a developer in Tampoi after a temporary bund failed, and may stop work if it does not comply.
How much is Johor spending on flood mitigation in Johor Bahru?
RM35.36 million for 20 projects across six river basins, announced in November 2026.
Which Johor Bahru areas flooded in November 2026?
Twelve main areas, including Kampung Mohd Amin, Kampung Pasir, Jalan Yahya Awal and the area around Hospital Sultanah Aminah, after about 120mm of rain in two hours.
What flood works are planned in the Sungai Chat basin?
Four projects worth RM8.5 million: deepening the Taman Merdeka and Tepian Tebrau retention ponds and building two new ponds, due between December 2026 and September 2027.
The Johor government is funding 20 flood mitigation projects worth RM35.36 million in Johor Bahru after flash floods hit 12 main areas of the city, including Kampung Mohd Amin, Kampung Pasir, Jalan Yahya Awal and Hospital Sultanah Aminah, Media Digital Johor reported on 6 November 2026. About 120mm of rain fell in two hours.
The projects
- Scope: six river basins and related roads: bigger retention ponds, new retention facilities, upgraded drains and culverts, more pumping capacity and new floodgates
- Sungai Chat basin: four projects worth RM8.5 million: deepening the retention ponds at Taman Merdeka, opposite Medan Selera Tengku Petri, and at Tepian Tebrau, and building two new ponds, including one in front of Maktab Sultan Abu Bakar. The Tepian Tebrau work finished on 26 October; the new ponds are due from December 2026 to September 2027
- Kampung Mohd Amin: a second on-site detention tank, built by the Johor Bahru City Council (MBJB) for more than RM1 million
- Elsewhere: more pump capacity in the Sungai Abdul Samad basin; drainage upgrades and flood pumps at Kampung Pasir and Sungai Skudai; a retention pond and main drain upgrade at Jalan Ayer Molek and Jalan Yahya Awal; and drain, culvert and floodgate upgrades at Sungai Sengkuang and Jalan Ismail Sultan
- Who runs it: MBJB, the Drainage and Irrigation Department and the Public Works Department, with each project tracked for progress and how well it works after completion
A warning for builders
On 3 November a temporary earth bund failed at a serviced-apartment site in Damansara Aliff, Tampoi, sending muddy water onto the road. MBJB will issue two compounds, for failing to control earthworks and for dirtying the road, and order the developer to follow its erosion and sediment control plan and carry out repairs. A stop-work order will be considered if the developer does not comply. In Selangor, the state has halted all development in Puncak Alam after floods there on 5 November.
Cover photo: Johor Menteri Besar Onn Hafiz Ghazi's Facebook, via Media Digital Johor.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
Johor data-centre land at RM140 psf as deal values fall 44%
Paragon Globe is selling 65 acres in Iskandar Puteri to DayOne at RM140 psf as OCBC sees Johor gain from Singapore's limits. Industrial deal value fell 44%.
Mustafa's RM368m Capital City Mall buy awaits state consent
Mustafa has paid RM143.7m of the RM368m for 591 units at Capital City Mall in Tampoi, Johor Bahru, but State consent covers only 55 of them.
Impact Capital IPO at 22 sen; new Klang Valley, JB offices
Kuching IT firm Impact Capital lists 24 Nov after a 22 sen IPO. RM4.67m of the RM21.27m it raises goes to new rented offices, the biggest in the Klang Valley.