Genting wins: court halts Sycal's Genting Sky City project

Genting Malaysia BhdSycal Ventures BhdGenting HighlandsPahangBentongProperty Court CasesHillside Development
Scott Seow
Probationary Estate Agent · PEA 4428 · CID Realtors Sdn Bhd
Key takeaways
  • The High Court ruled on 30 April 2026 for Genting Highlands, Genting Malaysia and First World Hotels & Resorts, stopping the proposed Genting Sky City project and ordering the slope at the site restored.
  • The judge found no valid planning permission and excavation without valid earthworks approval or approved building plans, in breach of the hill and highland development guidelines and the National Physical Plan.
  • Developer GM Aero Support, contractor Sycal Bhd and four others must pay RM243,800 in damages and RM2 million in costs; their bid to stay the judgment was dismissed and they are appealing.
  • The planned 10 blocks of hotels, suites and parking, 27 to 56 storeys, sat about 100 metres from First World Hotel on slopes of 25° to 35° or more.
Quick answers

Why was the Genting Sky City project stopped?

The High Court found there was no valid planning permission and that excavation went ahead without valid earthworks approval or approved building plans, in breach of the hill development guidelines and the National Physical Plan.

Who sued over Genting Sky City?

Genting Highlands Bhd, Genting Malaysia Bhd and First World Hotels & Resorts Sdn Bhd, against developer GM Aero Support Sdn Bhd, contractor Sycal Bhd and four others, in 2020.

Can the Genting Sky City land still be developed?

The injunction covers the project and works examined at trial, leaving open future development on the land, according to the written grounds reported by NST.

The High Court has stopped the proposed Genting Sky City hotel project next to First World Hotel in Genting Highlands and ordered the slope at the site restored. The suit was brought by Genting Highlands Bhd, Genting Malaysia Bhd and First World Hotels & Resorts Sdn Bhd against six defendants, including developer GM Aero Support Sdn Bhd and contractor Sycal Bhd, a unit of Sycal Ventures Bhd. The judgment was given on 30 April 2026, and the written grounds are dated 29 October. The defendants are appealing.

The ruling

  • Stopped: no further building on the project except permitted restoration works, and the affected slopes must be restored, Sycal Ventures' 2026 annual report says
  • Money: the defendants must pay RM243,800 in general damages and RM2 million in costs, jointly and severally, with 5% interest a year. Their counterclaim, over what they said was wrongful blocking of access to the site, was dismissed
  • Approvals: Justice Aliza Sulaiman found there was "no extant, valid and subsisting planning permission" for the project, and that excavation went ahead without valid earthworks approval or approved building plans. The project breached the guidelines on development in hill and highland areas and the National Physical Plan, she said (FMT). The defendants had said the project was safe and approved
  • Slopes: the Genting companies said much of the site is steep hillside of 25° to 35° or more, Class 3 and 4 slopes, and that excavation, piling and slope-cutting began around November 2019 without valid approvals from the Bentong Municipal Council. The judge cited a court-appointed expert that the slopes needed strengthening before any phase could proceed. Works could undermine support for occupied buildings and the resort's outer ring road. A lack of landslides during the case did not prove safety, because works had been restrained, she said (EdgeProp, citing the grounds)
  • Not a ban on the land: the injunction covers the project and works examined at trial, leaving open future development on the land (EdgeProp, citing NST)

The project

  • What was planned: 10 blocks of hotels, commercial suites and parking northeast of First World Hotel, with hotel and suite blocks of 27 to 56 storeys. Genting put the site about 100 metres from its hotel
  • The trial: 76 days, from 2022. The other defendants were the project's consultant engineer, structural engineering firm, architect and town planner
Genting Sky City: how the court case went, from the 2020 suit to the 2026 appeal

Since the ruling

  • 8 October 2026: the High Court allowed a committal application over an alleged breach of an earlier injunction, against GM Aero Support, Sycal Bhd and their directors
  • 12 October: the defendants' bid for a stay of the judgment pending appeal was dismissed
  • 11 November: case management of their appeal at the Court of Appeal
  • 3 December: Genting's applications for leave to go to the Federal Court over earlier decisions on document use and committal
  • Debts settled in land: GM Aero Support is one of six companies settling debts owed to the Sycal group by handing over development land in Genting Sempah. The transfer document was signed on 27 October 2026 and completion is expected by early 2027. The land's size and value were not given