  • Binastra Builders and Dynamicz Sdn Bhd agreed on 23 November 2026 to end a RM160 million demolition and main building contract on Jalan Damansara, Damansara Perdana, Petaling Jaya.
  • Binastra had billed RM23.82 million, about 15% of the contract; the work was due to be finished on 30 July 2026.
  • Neither side can claim liquidated damages over the termination; the final account is still to be agreed.
  • Binastra said Dynamicz is revising how it will carry out the project and appoint contractors; the unbilled RM136.2 million is about 2% of Binastra's order book (our sums).
Quick answers

Why did Binastra's Damansara Perdana contract end?

Binastra and Dynamicz Sdn Bhd agreed on 23 November 2026 to end it so that Dynamicz can revise its project implementation plan and how it appoints contractors. Neither side admits liability or default.

How much had Binastra billed on the Dynamicz contract?

RM23.82 million of the RM160 million contract, about 15%, by 23 November 2026.

What was Binastra building in Damansara Perdana?

Demolition and main building works for an office development with 560 office units on the 3rd to 5th floors, on Lot 86342 and Lot PT 44017, Jalan Damansara.

Does the termination hurt Binastra's earnings?

Binastra expects no material effect apart from losing the rest of the contract, about RM136.2 million (our sums), from an order book of about RM6.7 billion.

Binastra Corporation Bhd and its client Dynamicz Sdn Bhd have agreed to end a RM160 million contract to demolish and build an office development on Jalan Damansara in Damansara Perdana, Petaling Jaya. Binastra told Bursa Malaysia that the two sides agreed on 23 November 2026 to terminate the contract, which its subsidiary Binastra Builders Sdn Bhd had accepted in August 2024. By then Binastra had billed RM23.82 million, about 15% of the contract value (our sums).

The contract

  • Awarded: Binastra Builders accepted the letter of award on 2 August 2024 and took possession of the site that day. The work was due to be finished on 30 July 2026.
  • The work: demolition and main building works for a development with four floors of offices (560 units) on the 3rd to 5th floors, a facilities floor on level 5A, a service area on basement levels 1 and 2, and lifts and lift lobbies from the ground floor to the 3rd floor, described as Zone 1.
  • Site: Lot 86342 and Lot PT 44017, Jalan Damansara, Damansara Perdana, Mukim Sungai Buloh, Petaling district.
  • Not given: the project's name, the building's total size and who owns Dynamicz. We found no other public information on the company.

Why it ended and what happens next

  • Reason: Binastra said the termination lets Dynamicz revise how it will carry out the project and how it will appoint contractors. Neither side admits liability or default.
  • No penalties: neither side can claim liquidated damages arising from the termination.
  • Final account: Binastra Builders stopped work on 23 November. Dynamicz will assess the work done so far; the final value, any payments still due and the release of retention money depend on both sides agreeing the final account under the contract.
  • Effect on Binastra: it expects no material effect on its earnings or net assets apart from losing the rest of the contract from its order book. The part not yet billed is about RM136.2 million, about 2% of the RM6.7 billion order book Binastra reported at 31 July 2026 (our sums).

Binastra's other work

Binastra builds high-rise homes, offices, data centres and warehouses. Its 2026 awards include RM1.18 billion from Exsim Lumba Kuda Sdn Bhd and RM742.9 million from Maxim Pelangi Sdn Bhd (both January), RM503 million and RM491.2 million for two data-centre plots for Exsim Sri Permai Sdn Bhd (February and July), RM316.5 million from HCK Sentral Sdn Bhd (March) and RM303.8 million for an automated warehouse in Bandar Bukit Raja, Klang, for PTT Synergy's PTT Synexis Sdn Bhd (November; our report). For the quarter to 31 July 2026 it reported a net profit of RM50.6 million.

Need help with your factory, plant or industrial land?

Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.

Related news