AME Elite wins RM120m Baltimore Aircoil job in Nilai
- AME Elite will build Baltimore Aircoil's Nilai factory and office for RM120m, from October 2026 to December 2027.
- The 18.2-acre site is in Kawasan Perindustrian Nilai; Phase 1 is a manufacturing facility of about 30,000 sq m.
- The award comes from Rock Link Sdn Bhd, a property investment company named as the project owner; BAC Malaysia will run the plant.
- BAC plans to invest US$150m over ten years and create up to 200 skilled jobs by 2035.
Who is building Baltimore Aircoil's plant in Nilai?
AME Elite's unit AME Construction Sdn Bhd, under a RM120 million award from the project owner, Rock Link Sdn Bhd.
How big is BAC's Nilai facility?
Phase 1 is a manufacturing facility of about 30,000 sq m with an engineering office, on an 18.2-acre site in Kawasan Perindustrian Nilai.
When will the BAC plant in Nilai be ready?
AME's 14-month contract runs from October 2026 to December 2027, and BAC expects the main plant to be fully complete by 2030.
How much is BAC investing in Malaysia?
US$150 million over ten years, with up to 200 skilled jobs by 2035, according to MIDA.
AME Elite Consortium Bhd's construction unit, AME Construction Sdn Bhd, accepted a RM120 million award on 27 October 2026 to build a single-storey detached factory, a two-storey office and support buildings in Kawasan Perindustrian Nilai, Negeri Sembilan. The plant is for BAC Malaysia Sdn Bhd, the local unit of US cooling-equipment maker Baltimore Aircoil Company (BAC), and will be BAC's Asia-Pacific manufacturing and technical hub. The work runs 14 months, from October 2026 to December 2027.
The award comes from Rock Link Sdn Bhd, which AME names as the project owner. Rock Link is a Malaysian company set up in 2003 for general trading and property investment. BAC Malaysia will run the plant once it is finished; the filing does not say whether BAC will rent it or buy it.
The project
- Site: four lots, PT 51885 to PT 51888, on Jalan TS Utama, Mukim Labu, Seremban. MIDA put the site at 18.2 acres, about 792,800 sq ft
- Phase 1: a manufacturing facility of about 30,000 sq m (about 323,000 sq ft) with a regional engineering and manufacturing office, due by the end of 2027. This is the part AME is building
- Phase 2: an R&D centre and more advanced manufacturing technology. BAC expects the main plant to be fully complete by 2030
- Products: closed-circuit cooling towers, adiabatic coolers, hybrid and liquid cooling systems for data centres, industry and commercial buildings. A climate-controlled laboratory will test equipment for tropical climates
- Standards: the plant is designed to LEED Gold and FM Approved standards
BAC's US$150 million plan
BAC broke ground in Nilai on 5 August 2026. MIDA said the project is a planned investment of US$150 million over ten years and should create up to 200 skilled jobs by 2035, including engineering and professional roles. BAC's head of Asia-Pacific, Ted Lim, said the plant would bring the company closer to its customers and partners in the region and support its fast-growing industrial and digital infrastructure.
- Bursa Malaysia — AME Elite: letter of award from Rock Link Sdn Bhd, with press release (27 Oct 2026)
- MIDA — BAC breaks ground on US$150 million manufacturing facility in Malaysia (5 Aug 2026)
- Bursa Malaysia — AME Elite results for the quarter to 30 June 2026 (27 Aug 2026)
Facts summarised in our own words, with our own analysis added.
Setting up a factory or plant? Buying / selling industrial property or land in Malaysia? Reach out to Scott now.
Related news
AME Elite Consortium profile: parks, land and contracts
AME Elite Consortium develops and builds industrial parks in Johor, Penang and Selangor. Its parks, land bank, contracts and deals, kept up to date.
UEM Sunrise, AME Elite: RM972m land deal for RM4b Johor park
UEM Sunrise is selling 402 acres in Gerbang Nusajaya to its 50:50 JV with AME Elite for RM972.1m (RM55.50 psf) for a RM4b park. Plans went in on 2 Nov.
Northern TechValley @ BKE sold RM137m in its first year
AME and Majestic Gen’s 176-acre freehold park beside the BKE sold RM137.3m of factories in its first full year. Phase 1: 20 acres of 1½-storey detached units.